ABSTRACT

Time extension refers to time extended beyond Contract Deadlines by Owner. Contract Deadlines generally are the dates on which the completion of the following activities falls due to (1) mechanical completion, (2) ready for start-up of the plant, and (3) provisional acceptance certificate issuance. For claiming time extension, Contractor does schedule analysis and seeks to prove. For concurrent delays, Contractor is not eligible for prolongation cost when Owner approves time extension.