ABSTRACT

Prepare tender bid for external works or landscape project; measured works contract; inclusive of bid preparation, provisional programme and method statements Measured works bid; measured bills provided by the employer; project value

£30,000.00 nr 375.00 £50,000.00 nr 600.00 £100,000.00 nr 1275.00 £200,000.00 nr 1975.00 £500,000.00 nr 2500.00 £1,000,000.00 nr 3500.00

Lump sum bid; scope document, drawings and specification provided by the employer; project value

£30,000.00 nr 740.00 £50,000.00 nr 960.00 £100,000.00 nr 1850.00 £200,000.00 nr 3150.00 £500,000.00 nr 4250.00 £1,000,000.00 nr 6400.00

Prepare and maintain Health and Safety file; prepare risk and COSHH assessments, method statements, works programmes before the start of works on site; project value

£35,000.00 nr 280.00 £75,000.00 nr 420.00 £100,000.00 nr 560.00 £200,000.00-£500,000.00 nr 1400.00

Contract management Site management by site surveyor carrying out supervision and administration duties only; inclusive of oncosts

full time management week 1200.00 managing one other contract week 600.00

Parking Parking expenses where vehicles do not park on the site area; per vehicle

metropolitan area; city centre week 200.00 metropolitan area; outer areas week 160.00 suburban restricted parking areas week 40.00

Congestion charging London only week 58.00

£ Excluding site overheads and profit

SITE SETUP AND SITE ESTABLISHMENT

Site fencing; supply and erect temporary protective fencing and remove at completion of works Cleft chestnut paling

1.20m high 75mm larch posts at 3m centres 100m 1725.00 1.50m high 75mm larch posts at 3m centres 100m 1900.00

Heras fencing 2 week hire period 100m 990.00 4 week hire period 100m 1450.00 8 week hire period 100m 2350.00 12 week hire period 100m 3250.00 16 week hire period 100m 4150.00 24 week hire period 100m 6000.00

Site compounds Establish site administration area on reduced compacted Type 1 base; 150mm thick; allow for initial setup of site office and welfare facilities for site manager and maximum eight site operatives

temporary base or hard standing; 20× 10m 200m2 3250.00

To hardstanding area above; erect office and welfare accommodation; allow for furniture, telephone connection, and power; restrict access using temporary safety fencing to the perimeter of the site administration area Establishment; delivery and collection costs only

site office and chemical toilet; 20m of site fencing nr 990.00 site office and chemical toilet; 40m of site fencing nr 1075.00 site office and chemical toilet; 60m of site fencing nr 1150.00

Weekly hire rates of site compound equipment site office 2.4×3.6m; chemical toilet; 20m of site fencing week 105.00 site office 4.8×2.4m; chemical toilet; 20m of site fencing; armoured store 2.4×3.6m week 120.00 site office 2.4×3.6m; chemical toilet; 40m of site fencing week 150.00 site office 2.4×3.6m; chemical toilet; 60m of site fencing week 195.00

Removal of site compound Remove base; fill with topsoil and reinstate to turf on completion of site works 200m2 1975.00

Surveying and setting out Note: In all instances a quotation should be obtained from a surveyor. The following cost projections are based on the costs of a surveyor using EDM (electronic distance measuring equipment) where an average of 400 different points on site are recorded in a day. The surveyed points are drawn in a CAD application and the assumption used that there is one day of drawing up for each day of on site surveying. Survey existing site using laser survey equipment and produce plans of existing site conditions

site 1000 to 10,000m2 with sparse detail and features; boundary and level information only; average five surveying stations nr 750.00 site up to 1000m2 with dense detail such as buildings, paths, walls and existing vegetation; average five survey stations nr 1500.00 site up to 4000m2 with dense detail such as buildings, paths, walls and existing vegetation; average 10 survey stations nr 2250.00