ABSTRACT

FACTA AA; double seal 450× 450mm (560×560mm) 122.09 1.50 35.63 – 134.22 nr 169.85 600× 450mm (710×560mm) 134.15 1.80 42.75 – 147.63 nr 190.38 600× 600mm (710×710mm) 146.36 2.00 47.50 – 162.53 nr 210.03

FACTA AAA; single seal 450× 450mm (520×520mm) 115.75 1.50 35.63 – 127.88 nr 163.51 600× 450mm (670×520mm) 124.92 1.80 42.75 – 138.40 nr 181.15 600× 600mm (670×670mm) 133.10 2.00 47.50 – 149.27 nr 196.77

FACTA AAA; double seal 450mm×450mm (560×560) 147.36 1.50 35.63 – 159.49 nr 195.12 600mm×450mm (710×560) 161.00 1.80 42.75 – 174.48 nr 217.23 600mm×600mm (710×710) 179.30 2.00 47.50 – 195.47 nr 242.97

FACTA B; single seal 450× 450mm (520×520mm) 97.15 1.50 35.63 – 109.28 nr 144.91 600× 450mm (670×520mm) 121.29 1.80 42.75 – 134.77 nr 177.52 600× 600mm (670×670mm) 141.00 2.00 47.50 – 157.17 nr 204.67

FACTA B; double seal 450× 450mm (560×560mm) 140.20 1.50 35.63 – 152.33 nr 187.96 600× 450mm (710×560mm) 156.08 1.80 42.75 – 169.56 nr 212.31 600× 600mm (710×710mm) 187.43 2.00 47.50 – 203.60 nr 251.10

Access covers and frames; recessed; galvanized; Steelway Brickhouse; Bripave; bedding frame in cement:mortar (1:3); cover in grease and sand; clear opening sizes; base size shown in brackets (for block depths 50mm, 65mm, 80mm or 100mm) FACTA AA

450× 450mm (562×562mm) 217.84 1.50 35.63 – 229.97 nr 265.60 600× 450mm (712×562mm) 238.97 1.80 42.75 – 252.45 nr 295.20 600× 600mm (712×712mm) 247.68 2.00 47.50 – 263.29 nr 310.79 750× 600mm (862×712mm) 276.37 2.40 57.00 – 293.89 nr 350.89

FACTA B 450× 450mm (562×562mm) 218.22 1.50 35.63 – 230.35 nr 265.98 600× 450mm (712×562mm) 253.68 1.80 42.75 – 267.16 nr 309.91 600× 600mm (712×712mm) 256.84 2.00 47.50 – 273.01 nr 320.51 750× 600mm (862×712mm) 257.67 2.40 57.00 – 275.19 nr 332.19

FACTA D 450× 450mm (562×562mm) 244.57 1.50 35.63 – 256.70 nr 292.33 600× 450mm (712×562mm) 259.85 1.80 42.75 – 273.33 nr 316.08 600× 600mm (712×712mm) 268.47 2.00 47.50 – 284.64 nr 332.14 750× 600mm (862×712mm) 326.73 2.40 57.00 – 344.25 nr 401.25

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

ACCESS COVERS AND FRAMES – cont

Access covers and frames; Jones of Oswestry; bedding frame in cement:mortar (1:3); cover in grease and sand; clear opening sizes Access covers and frames; Suprabloc; to paved areas; filling with blocks cut and fitted to match surrounding paving

pedestrian weight; 300×300mm 199.21 2.50 59.38 – 207.38 nr 266.76 pedestrian weight; 450×450mm 339.92 2.50 59.38 – 339.92 nr 399.30 pedestrian weight; 450×600mm 378.58 2.50 59.38 – 387.09 nr 446.47 light vehicular weight; 300×300mm 255.22 2.40 57.00 – 263.39 nr 320.39 light vehicular weight; 450×450mm 196.77 3.00 71.25 – 206.14 nr 277.39 light vehicular weight; 450×600mm 390.92 4.00 95.00 – 399.09 nr 494.09 heavy vehicular weight; 300× 300mm 255.79 3.00 71.25 – 264.30 nr 335.55 heavy vehicular weight; 450× 600mm 405.26 3.00 71.25 – 414.63 nr 485.88 heavy vehicular weight; 600× 600mm 475.60 4.00 95.00 – 489.22 nr 584.22

Extra over manhole frames and covers for

filling recessed manhole covers with brick paviors; PC £450.00/1000 17.60 1.00 23.75 – 18.21 m2 41.96 filling recessed manhole covers with vehicular paving blocks; PC £10.51/m2 10.51 0.75 17.81 – 11.12 m2 28.93 filling recessed manhole covers with concrete paving flags; PC £16.20/m2 16.20 0.35 8.31 – 16.56 m2 24.87

CHANNELS

Best quality vitrified clay half section channels; Hepworth Plc; bedding and jointing in cement:mortar (1:2) Channels; straight

100mm 8.17 0.80 19.00 – 11.46 m 30.46 150mm 13.60 1.00 23.75 – 16.89 m 40.64 225mm 30.54 1.35 32.06 – 33.82 m 65.88 300mm 62.69 1.80 42.75 – 65.97 m 108.72

Bends; 15, 30, 45 or 90° 100mm bends 7.36 0.75 17.81 – 9.00 nr 26.81 150mm bends 12.72 0.90 21.38 – 15.19 nr 36.57 225mm bends 49.28 1.20 28.50 – 52.57 nr 81.07 300mm bends 100.46 1.10 26.13 – 104.58 nr 130.71

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Best quality vitrified clay channels; Hepworth Plc; bedding and jointing in cement:mortar (1:2) Branch bends; 15, 30, 45 or 90°; left or right hand

100mm 7.36 0.75 17.81 – 9.00 nr 26.81 150mm 12.72 0.90 21.38 – 15.19 nr 36.57

CLARIFICATION ON LABOUR COSTS IN THIS SECTION

General groundworks team Generally a three man team is used in this section; The column Labour hours reports team hours. The column Labour £ reports the total cost of the team for the unit of work shown

3man team – 1.00 71.25 – – hr 71.25

EXCAVATION FOR DRAINAGE

Machine excavation Excavating pits; starting from ground level; works exclude for earthwork retention

maximum depth not exceeding 1.00m – 0.50 11.88 17.78 – m3 29.66 maximum depth not exceeding 2.00m – 0.50 11.88 29.16 – m3 41.04 maximum depth not exceeding 4.00m – 0.50 11.88 75.65 – m3 87.53

Disposal of excavated material; depositing on site in permanent spoil heaps; average 50m – 0.04 0.99 2.36 – m3 3.35 Filling to excavations; obtained from on site spoil heaps; average thickness not exceeding 0.25m – 0.13 3.17 6.72 – m3 9.89

Hand excavation Excavating pits; starting from ground level; works exclude for earthwork retention

maximum depth not exceeding 1.00m – 1.20 57.00 – – m3 57.00 maximum depth not exceeding 2.00m – 1.50 71.25 – – m3 71.25

Works to pits or drainage excavations Surface treatments; compacting; bottoms of excavations – 0.05 1.19 – – m2 1.19

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

EXCAVATION FOR DRAINAGE – cont

Earthwork support Manhole boxes to excavations (not included); Timber plywood with timber braces to shore excavations to 1.00m deep; opposing faces distance less than 1.00m

1.00m deep – 0.50 23.75 – 9.35 m2 33.10 2.00m deep – 1.00 47.50 – 9.35 m2 56.85

Trench boxes; A-Plant Manhole box soil retention – 0.50 35.63 166.30 – week 201.93 Placement of manhole protection system to 3.0m deep to enable earthwork retention; maximum distance between opposing faces 1.8m – 0.50 35.63 225.30 – week 260.93

GULLIES AND INTERCEPTION TRAPS

Intercepting traps; Hepworth Plc Vitrified clay; inspection arms; brass stoppers; iron levers; chains and staples; galvanized; staples cut and pinned to brickwork; cement:mortar (1:2) joints to vitrified clay pipes and channels; bedding and surrounding in concrete; 11.50N/mm2-40mm aggregate; cutting and fitting brickwork; making good facings

100mm inlet; 100mm outlet 106.89 3.00 71.25 – 115.49 nr 186.74 150mm inlet; 150mm outlet 154.12 2.00 47.50 – 167.66 nr 215.16

Gullies; concrete; FP McCann

Concrete road gullies; trapped; cement:mortar (1:2) joints to concrete pipes; bedding and surrounding in concrete; 11.50N/mm2-40mm aggregate; rodding eye; stoppers

375mm diameter × 750mm deep 48.02 3.00 142.50 – 71.28 nr 213.78 375mm diameter × 900mm deep 49.99 3.00 142.50 – 73.25 nr 215.75 450mm diameter × 750mm deep 50.01 3.00 142.50 – 73.27 nr 215.77 450mm diameter × 900mm deep 54.18 3.00 142.50 – 77.44 nr 219.94 450mm diameter × 1.05m deep 58.40 3.50 166.25 – 81.66 nr 247.91 450mm diameter × 1.20m deep 75.10 4.00 190.00 – 98.36 nr 288.36

Accessories for clay gullies coverslab 21.37 0.25 11.88 – 21.37 nr 33.25 seating rings 22.58 – – – 22.58 nr 22.58

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Gullies; vitrified clay; Hepworth Plc; bedding in concrete; 11.50N/mm240mm aggregate Yard gullies (mud); trapped; domestic duty (up to 1 tonne)

100mm outlet; 100mm diameter; 225mm internal width; 585mm internal depth 139.00 3.50 83.13 – 139.71 nr 222.84 150mm outlet; 100mm diameter; 225mm internal width; 585mm internal depth 139.00 3.50 83.13 – 139.71 nr 222.84

Yard gullies (mud); trapped; medium duty (up to 5 tonnes)

100mm outlet; 100mm diameter; 225mm internal width; 585mm internal depth 196.51 3.50 83.13 – 197.21 nr 280.34 150mm outlet; 100mm diameter; 225mm internal width; 585mm internal depth 215.31 3.50 83.13 – 216.01 nr 299.14

Combined filter and silt bucket for yard gullies

225mm diameter 50.26 – – – 50.26 nr 50.26 Road gullies; trapped with rodding eye

100mm outlet; 300mm internal diameter; 600mm internal depth – 3.50 83.13 – 134.39 nr 217.52 150mm outlet; 300mm internal diameter; 600mm internal depth 136.91 3.50 83.13 – 137.61 nr 220.74 150mm outlet; 400mm internal diameter; 750mm internal depth 158.78 3.50 83.13 – 159.49 nr 242.62 150mm outlet; 450mm internal diameter; 900mm internal depth 214.82 3.50 83.13 – 215.53 nr 298.66

Hinged gratings and frames for gullies; alloy

193mm for 150mm diameter gully – – – – 33.32 nr 33.32 120× 120mm – – – – 11.85 nr 11.85 150× 150mm – – – – 21.43 nr 21.43 230× 230mm – – – – 39.18 nr 39.18 316× 316mm – – – – 103.87 nr 103.87

Hinged gratings and frames for gullies; cast iron

265mm for 225mm diameter gully – – – – 66.56 nr 66.56 150× 150mm – – – – 21.43 nr 21.43 230× 230mm – – – – 39.18 nr 39.18 316× 316mm – – – – 103.87 nr 103.87

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

GULLIES AND INTERCEPTION TRAPS – cont

Universal gully trap PVC-u; Wavin Plastics Ltd; OsmaDrain system; bedding in concrete; 11.50N/mm240mm aggregate Universal gully fitting; comprising gully trap only

110mm outlet; 110mm diameter; 205mm internal depth 14.87 3.50 83.13 – 15.57 nr 98.70

Vertical inlet hopper; c\w plastic grate 272× 183mm 19.98 0.25 5.94 – 19.98 nr 25.92

Sealed access hopper 110×110mm 46.99 0.25 5.94 – 46.99 nr 52.93

Universal gully PVC-u; Wavin Plastics Ltd; OsmaDrain system; accessories to universal gully trap Hoppers; backfilling with clean granular material; tamping; surrounding in lean mix concrete

plain hopper; with 110mm spigot; 150mm long 16.34 0.40 9.50 – 16.76 nr 26.26 vertical inlet hopper; with 110mm spigot; 150mm long 19.98 0.40 9.50 – 19.98 nr 29.48 sealed access hopper; with 110mm spigot; 150mm long 46.99 0.40 9.50 – 46.99 nr 56.49 plain hopper; solvent weld to trap 11.16 0.40 9.50 – 11.16 nr 20.66 vertical inlet hopper; solvent wed to trap 19.17 0.40 9.50 – 19.17 nr 28.67 sealed access cover; PVC-u 23.93 0.10 2.38 – 23.93 nr 26.31

Gullies PVC-u; Wavin Plastics Ltd; OsmaDrain system; bedding in concrete; 11.50N/mm2-40mm aggregate Bottle gully; providing access to the drainage system for cleaning

bottle gully; 228×228×317mm deep 99.18 0.50 11.88 – 99.78 nr 111.66 sealed access cover; PVC-u; 217× 217mm 30.84 0.10 2.38 – 30.84 nr 33.22 grating; ductile iron; 215×215mm 23.78 0.10 2.38 – 23.78 nr 26.16 bottle gully riser; 325mm 5.65 0.50 11.88 – 6.95 nr 18.83

Yard gully; trapped; 300mm diameter × 600mm deep; including catchment bucket and ductile iron cover and frame; medium duty loading

305mm diameter × 600mm deep 246.18 2.50 59.38 – 250.05 nr 309.43

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Kerbs to gullies One course Class B engineering bricks to four sides; rendering in cement: mortar (1:3); dished to gully gratings

150× 150mm 2.25 0.33 7.92 – 2.68 nr 10.60

INSPECTION CHAMBERS AND MANHOLES

Inspection chambers; in situ concrete; excavations; earthwork reinforcement all not included Beds; plain in situ concrete; 11.50N/mm2-40mm aggregate

thickness not exceeding 150mm – 2.00 47.50 – 115.88 m3 163.38 thickness 150-450mm – 1.75 41.56 – 115.88 m3 157.44

Benchings in bottoms; plain in situ concrete; 25.50N/mm2-20mm aggregate

thickness 150-450mm – 2.00 47.50 – 115.88 m3 163.38 Isolated cover slabs; reinforced In situ concrete; 21.00N/mm2-20mm aggregate

thickness not exceeding 150mm 115.88 4.00 95.00 – 115.88 m3 210.88 Fabric reinforcement; A193 (3.02 kg/m2) in cover slabs 1.87 0.06 1.49 – 1.87 m2 3.36 Formwork to reinforced in situ concrete; isolated cover slabs

soffits; horizontal – 3.28 77.90 – 4.25 m2 82.15 height not exceeding 250mm – 0.97 23.04 – 1.71 m 24.75

Inspection chambers (House – HIC); precast concrete units; to excavations, earthwork reinforcement, in situ bases benchings all priced separately; includes cover slab Precast concrete inspection chamber units; FP McCann Ltd; bedding, jointing and pointing in cement:mortar (1:3); 600×450mm internally

600mm deep 50.45 6.50 154.38 – 57.17 nr 211.55 900mm deep 67.20 7.00 166.25 – 72.31 nr 238.56

Drainage chambers; FP McCann Ltd; 1200×750mm; no base unit; depth of invert

1.00m deep 185.32 3.00 213.75 – 193.83 nr 407.58 1.50m deep 237.04 3.67 261.25 – 250.66 nr 511.91 2.00m deep 288.76 4.17 296.88 – 305.79 nr 602.67

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

INSPECTION CHAMBERS AND MANHOLES – cont

Bases to chamber ring manholes; in situ concrete; to excavated ground (not included); on 50mm ST2 blinding on 225mm mass concrete to receive bottom manhole ring blinded with 50mm ST2 blinding Diameter of manhole

900mm – 4.00 190.00 – 33.96 nr 223.96 1.05m – 4.00 190.00 – 41.09 nr 231.09 1.20m – 4.50 213.75 – 57.39 nr 271.14 1.50m – 5.50 261.25 – 86.93 nr 348.18

Bottom manhole chamber ring; FP McCann Ltd; including pipe entrances to bases (not included); forming pipe entrances to manhole ring; seating and sealing to base; connecting pipes (not included); depth 1.00m; diameter

900mm 78.45 3.00 213.75 93.19 86.96 nr 393.90 1.05m 82.71 3.25 231.56 93.19 91.22 nr 415.97 1.20m 100.98 4.00 285.00 116.48 109.49 nr 510.97 1.50m 176.30 4.50 320.63 139.78 184.81 nr 645.22

Benchings to manholes; 400mm concrete; diameter of manhole

900mm – 0.75 35.63 – 46.74 nr 82.37 1.05m – 0.75 35.63 – 65.43 nr 101.06 1.20m – 0.90 42.75 – 84.13 nr 126.88 1.50m – 1.10 52.25 – 132.76 nr 185.01

Easi-Base Polypropylene liner; FP McCann Ltd; complete with prefabricated benching and channels as one unit; Easi-Base diameter

1200mm 427.45 1.00 47.50 46.59 427.45 nr 521.54 1500mm 854.90 1.00 47.50 46.59 854.90 nr 948.99

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Concrete manhole chamber rings; FP McCann Ltd; standard ring units to excavated ground (not included); sealed with bitumen tape; tongue and groove units installed to 1.00m deep base units (not included); surrounding in concrete min 150 thick and backfilling; Note: The final depths shown below show operations onto the 1.00m deep base rings above Internal diameter 900mm; final manhole depth

1.00m deep – 1.00 71.25 46.59 86.31 nr 204.15 Internal diameter 1.05mm; final manhole depth

1.00m deep – 1.00 71.25 93.19 86.31 nr 250.75 2.00m deep 82.71 2.50 178.13 163.08 246.81 nr 588.02 3.00m deep 165.42 4.00 285.00 186.38 406.07 nr 877.45

Internal diameter 1200mm; final manhole depth

1.00m deep – 1.00 71.25 139.78 86.31 nr 297.34 2.00m deep 100.98 3.00 213.75 186.38 265.08 nr 665.21 3.00m deep 201.96 4.00 285.00 279.56 442.61 nr 1007.17

Internal diameter 1500mm 1.00m deep – 2.00 142.50 139.78 86.31 nr 368.59 2.00m deep 176.30 4.00 285.00 186.38 340.40 nr 811.78 3.00m deep 352.60 5.00 356.25 279.56 593.25 nr 1229.06

Concrete manhole chamber rings; Wide wall; FP McCann Ltd; 130mm thick precast manholes; (concrete surround on backfill not required) to excavated ground (not included); Water-tight, complete with sealant; to prepared base (or Easi-Base priced elsewhere) Internal diameter 1200mm

1.00m deep 169.95 3.00 213.75 139.78 169.95 nr 523.48 2.00m deep 339.90 4.00 285.00 186.38 339.90 nr 811.28 3.00m deep 509.85 6.00 427.50 232.97 509.85 nr 1170.32

Internal diameter 1500mm 1.00m deep 267.80 3.00 213.75 186.38 276.31 nr 676.44 2.00m deep 535.60 – – – – nr – 3.00m deep 803.40 7.00 498.75 326.16 811.91 nr 1636.82

Cover slabs for chambers or shaft sections; FP McCann Ltd; heavy duty 900mm diameter internally 79.70 0.67 15.82 – 79.70 nr 95.52 1050mm diameter internally 85.53 2.00 47.50 17.08 85.53 nr 150.11 1200mm diameter internally 103.74 1.00 23.75 17.08 103.74 nr 144.57

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

INSPECTION CHAMBERS AND MANHOLES – cont

Cover slabs for chambers or shaft sections – cont 1500mm diameter internally 188.81 1.00 23.75 17.08 188.81 nr 229.64 1800mm diameter internally 310.01 2.00 47.50 38.44 310.01 nr 395.95

Brickwork Walls to manholes; bricks; PC £400.00/ 1000; in cement:mortar (1:3)

one brick thick 50.40 3.00 71.25 – 60.62 m2 131.87 one and a half brick thick 75.60 4.00 95.00 – 90.92 m2 185.92 two brick thick projection of footing or the like 100.80 4.80 114.00 – 121.23 m2 235.23

Walls to manholes; engineering bricks; in cement:mortar (1:3)

one brick thick 56.70 3.00 71.25 – 66.92 m2 138.17 one and a half brick thick 85.05 4.00 95.00 – 100.37 m2 195.37 two brick thick projection of footing or the like 113.40 4.80 114.00 – 133.83 m2 247.83

Extra over common or engineering bricks in any mortar for fair face; flush pointing as work proceeds; English bond walls or the like – 0.13 3.17 – – m2 3.17 In situ finishings; cement:sand mortar (1:3); steel trowelled; 13mm one coat work to manhole walls; to brickwork or blockwork base; over 300mm wide – 0.80 19.00 – 3.41 m2 22.41 Building into brickwork; ends of pipes; making good facings or renderings

small – 0.20 4.75 – – nr 4.75 large – 0.30 7.13 – – nr 7.13 extra large – 0.40 9.50 – – nr 9.50 extra large; including forming ring arch cover – 0.50 11.88 – – nr 11.88

Inspection chambers; polypropylene; Hepworth Plc Mini access chamber; up to 600mm deep; including cover and frame

300mm diameter × 600mm deep; three 100/110mm inlets 177.66 3.00 71.25 – 180.66 nr 251.91

Up to 1200mm deep; including polymer cover and frame with screw down lid

475mm diameter × 940mm deep; five 100/110mm inlets; supplied with four stoppers in inlets 262.65 4.00 95.00 – 350.57 nr 445.57

Extra for square ductile iron cover and frame to 1 tonne load; screw down lid 129.45 – – – 44.53 nr 44.53

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Step irons; drainage systems; malleable cast iron; galvanized; building into joints General purpose pattern; for one brick walls 4.03 0.17 4.04 – 4.03 nr 8.07 Accessories in PVC-u

110mm screwed access cover 2.52 – – – 2.52 nr 2.52 110mm rodding eye 17.99 0.50 11.88 – 23.00 nr 34.88

Kerbs; to gullies; in one course Class B engineering bricks; to four sides; rendering in cement:mortar (1:3); dished to gully gratings 3.78 1.00 23.75 – 4.80 nr 28.55

CAST IRON DRAINAGE

Cast iron pipes and fittings; PAM; Timesaver 100mm cast iron pipes double spiggot; in trenches (trenches not included)

laid straight 52.56 0.11 5.28 – 52.56 m 57.84 short runs under 3.00m 71.06 0.17 7.92 – 71.06 m 78.98

Extra over 100mm cast iron pipes for bends; medium radius – 87.5°–60° 107.41 0.33 7.84 – 107.41 nr 115.25 bends; medium radius – 45°–10° 99.61 0.33 7.84 – 99.61 nr 107.45 bends; long radius 141.29 0.25 5.94 – 141.29 nr 147.23 plain branch 124.35 0.25 5.94 – 124.35 nr 130.29

150mm cast iron pipes; in trenches (trenches not included)

laid straight 91.38 0.13 5.94 – 91.38 m 97.32 short runs under 3.00m 113.80 0.25 11.88 – 113.80 m 125.68

Extra over 150mm cast iron pipes for bends; medium radius – 87.5°–60° 136.26 0.33 7.84 – 136.26 nr 144.10 bends; medium radius – 45°–10° 162.83 0.33 7.84 – 162.83 nr 170.67

225mm cast iron pipes; in trenches (trenches not included)

laid straight 317.05 0.20 9.50 – 317.05 m 326.55 short runs under 3.00m 317.05 0.50 23.75 – 317.05 m 340.80

Extra over 225mm cast iron pipes for bends; medium radius – 87.5°–10° – 0.50 11.88 – 400.95 nr 412.83

Cast iron inspection chambers; PAM; Timesaver; drainage systems bolted flat covers; bedding in cement: mortar (1:3); mechanical coupling joints 100×100mm

one branch each side 242.74 1.50 71.25 – 299.94 nr 371.19 two branches each side 477.86 2.50 118.75 – 646.03 nr 764.78

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

CAST IRON DRAINAGE – cont

Cast iron inspection chambers – cont 100×150mm

one branch each side 437.24 2.00 95.00 – 437.58 nr 532.58 two branch each side 828.69 2.50 118.75 – 829.04 nr 947.79

150×150mm one branch each side 399.10 2.50 118.75 – 533.91 nr 652.66 two branches each side 796.92 3.00 142.50 – 998.97 nr 1141.47

Accessories in Cast iron Gullies; including concrete bed and surround

Gully trap with surface access 100mm ×87.5° 253.70 1.00 47.50 – 284.57 nr 332.07 Gully trap with 225mm inlet 222.77 1.00 47.50 – 253.64 nr 301.14 Trapless gully 249.15 1.00 47.50 – 280.02 nr 327.52 Gully trap square 225× 225mm with sediment trap and grate 502.54 1.00 47.50 – 533.41 nr 580.91 Deans trap gully 600mm deep inclusive of sediment pan 587.58 1.00 47.50 – 618.45 nr 665.95 Road Gully including hinged grate and frame 677.14 3.00 142.50 – 708.01 nr 850.51

LINEAR DRAINAGE

Marshalls Plc; Mini Beany combined kerb and channel drainage system; to trenches (not included) Precast concrete drainage channel base; 185-385mm deep; bedding, jointing and pointing in cement:mortar (1:3); on 150mm deep concrete (ready mixed) foundation; including haunching with in situ concrete; 11.50N/mm2 – 40mm aggregate one side; channels 250mm wide×1.00m long

straight; 1.00m long 33.97 1.00 23.75 – 38.10 m 61.85 straight; 500mm long 38.08 1.05 24.94 – 42.21 m 67.15 radial; 30/10 or 9/6 internal or external 35.19 1.33 31.67 – 39.32 m 70.99 angles 45 or 90° 101.59 1.00 23.75 – 105.72 nr 129.47

Mini Beany Top Block; perforated kerb unit to drainage channel above; natural grey

straight 40.37 0.33 7.92 – 41.87 m 49.79 radial; 30/10 or 9/6 internal or external 25.07 0.50 11.88 – 26.57 m 38.45 angles 45 or 90° 101.14 0.50 11.88 – 102.64 nr 114.52

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Mini Beany; outfalls; two section concrete trapped outfall with Mini Beany cast iron access cover and frame; to concrete foundation

high capacity outfalls; silt box 150/ 225mm outlet; two section trapped outfall silt box and cast iron access cover 330.70 1.00 23.75 – 702.81 nr 726.56 inline side or end outlet; outfall 150mm; 2 section concrete trapped outfall; cast iron Mini Beany access cover and frame 548.20 1.00 23.75 – 549.05 nr 572.80

Ancillaries to Mini Beany end cap 20.06 0.25 5.94 – 20.06 nr 26.00 end cap outlets 52.84 0.25 5.94 – 52.84 nr 58.78

Precast concrete channels; Charcon Hard Landscaping; on 150mm deep concrete foundations; including haunching with in situ concrete; 21.00N/mm2 – 20mm aggregate; both sides Charcon Highway Precast drainage channel

Safetycurb; 250×250mm 44.92 0.67 15.83 – 64.62 m 80.45 Charcon Safeticurb; slotted safety channels; for heavy vehicles

DBM; 248×248mm 80.12 0.80 19.00 – 99.82 m 118.82 Clearway; 324× 257mm 91.43 0.80 19.00 – 111.13 m 130.13

Silt box tops; concrete frame; cast iron grid lids; type 1; set over gully

457× 610mm 409.46 2.00 47.50 – 410.62 nr 458.12

Slot and Channel drains Loadings for slot drains A15; 1.5 tonne; pedestrian B125; 12.5 tonne; domestic use C250; 25 tonne; car parks, supermarkets, industrial units D400; 40 tonne; highways E600; 60 tonne; forklifts

Fully galvanized hexagonal format slot drains; Gatic Ltd; for paving or asphalt use; 269mm depth ‘Facade drain’ fixed to building facade to collect water falling from the building facade

115mm maximum flow rate 19.6 litres/second 37.00 0.33 15.83 – 37.00 m 52.83

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

LINEAR DRAINAGE – cont

Fully galvanized hexagonal format slot drains – cont Slotdrain channels; Hexagonally profiled fully galvanized slotdrain system; In trenched (not included) surrounded by concrete

Pavslot 10mm throat 100mm deep 45.00 0.33 15.83 – 47.75 m 63.58 Pavslot 10mm throat 150mm deep 50.00 0.33 15.83 – 52.88 m 68.71 Gatic Access points at 1nr per 30m per 30m 5.33 0.25 11.88 – 8.07 m 19.95 Gatic outlets 170.00 1.00 47.50 – 172.75 nr 220.25

Slot drains; ACO Technologies; laid to concrete bed C25 on compacted granular base on 200mm deep concrete bed; haunched with 200mm concrete surround; all in 750×430mm wide trench with compacted 200mm granular base surround (excavation and subbase not included) ACO MultiDrain M100PPD; recycled polypropylene drainage channel; range of gratings to complement installations which require discreet slot drainage

142mm wide×150mm deep 74.70 0.83 19.79 – 87.31 m 107.10 Accessories for M100PPD

connectors; vertical outlet 110mm 17.25 – – – 17.25 nr 17.25 connectors; vertical outlet 160mm 17.25 – – – 17.25 nr 17.25 sump units; 110mm 132.85 1.50 35.63 – 156.03 nr 191.66 universal gully and bucket; 440× 440×1315mm deep 793.05 3.00 71.25 – 836.50 nr 907.75

Channel drains; ACO Technologies; ACO MultiDrain MD polymer concrete channel drainage system; traditional channel and grate drainage solution ACO MultiDrain MD Brickslot; offset galvanized slot drain grating for M100PPD; load class C250

brickslot; galvanized steel; 1.00m 85.00 – – – 85.00 m 85.00 ACO MultiDrain MD Brickslot; offset slot drain grating; load class C250 – 400

brickslot; galvanized steel; 1000mm 158.80 1.20 28.50 – 158.80 m 187.30 brickslot; stainless steel; 1000mm 173.80 1.20 28.50 – 347.60 m 376.10

Accessories for MultiDrain MD sump unit; complete with sediment bucket and access unit 132.85 1.00 23.75 – 270.20 nr 293.95 end cap; closing piece 7.30 – – – 7.30 nr 7.30 end cap; inlet/outlet 7.30 – – – 7.30 nr 7.30

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

ACO Drainlock Gratings for M100PPD and M100D system A15 loading

slotted galvanized steel 23.05 0.15 3.56 – 23.05 m 26.61 perforated galvanized steel 42.10 0.15 3.56 – 42.10 m 45.66

C250 loading Heelguard composite black; 500mm long with security locking 55.10 – – – 55.10 m 55.10 Intercept; ductile iron; 500mm long 126.50 – – – 126.50 m 126.50 slotted galvanized steel; 1.00m long 59.60 – – – 59.60 m 59.60 perforated galvanized steel; 1.00m long 65.10 – – – 65.10 m 65.10 mesh galvanized steel; 1.00m long 44.60 – – – 44.60 m 44.60

Wade Ltd; stainless steel channel drains; specialized applications; bespoke manufacture Drain in stainless steel; c/w tie in lugs and inbuilt falls to 100mm spigot outlet; stainless steel gratings

NE channel; Ref 12430; secured gratings 420.00 1.20 28.50 – 432.61 m 461.11

PIPE LAYING

Excavating trenches; to receive pipes; grading bottoms to falls; backfilling with excavated material and compacting; disposal of surplus material off site; volumes allow for bedding materials which are priced separately below Trenches 300mm wide

depth of pipe 750mm – – – 9.89 5.25 m3 15.14 depth of pipe 900mm – – – 11.30 6.64 m3 17.94 depth of pipe 1.20m – – – 11.86 9.41 m3 21.27 depth of pipe 1.50m – – – 13.18 12.19 m3 25.37 depth of pipe 2.00m – – – 8.64 16.81 m3 25.45

Trenches 300mm wide depth of pipe 750mm – – – 3.30 3.47 m 6.77 depth of pipe 900mm – – – 4.00 4.16 m 8.16 depth of pipe 1.20m – – – 5.34 5.55 m 10.89 depth of pipe 1.50m – – – 6.68 6.93 m 13.61 depth of pipe 2.00m – – – 8.64 16.81 m 25.45

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

PIPE LAYING – cont

Earthwork support; providing support to opposing faces of excavation; moving along as work proceeds Maximum depth not exceeding 2.00m

distance between opposing faces not exceeding 2.00m – 0.80 19.00 27.32 – m 46.32

Excavating trenches; using 3 tonne tracked excavator; to receive pipes; grading bottoms; earthwork support; filling with excavated material to within 150mm of finished surfaces and compacting; completing fill with topsoil; disposal of surplus soil Services not exceeding 200mm nominal size

average depth of run not exceeding 0.50m 1.78 0.12 2.85 1.04 1.78 m 5.67 average depth of run not exceeding 0.75m 1.78 0.16 3.87 1.44 1.78 m 7.09 average depth of run not exceeding 1.00m 1.78 0.28 6.73 2.51 1.78 m 11.02 average depth of run not exceeding 1.25m 1.49 0.38 9.10 3.37 1.49 m 13.96

Granular beds to trenches; lay granular material to trenches excavated separately; to receive pipes (not included) 300mm wide×100mm thick

reject sand – 0.05 1.19 0.23 3.79 m 5.21 reject gravel – 0.05 1.19 0.23 3.44 m 4.86 shingle 40mm aggregate – 0.05 1.19 0.23 4.30 m 5.72 sharp sand 4.50 0.05 1.19 0.23 4.50 m 5.92

300mm wide×150mm thick reject sand – 0.08 1.78 0.35 5.69 m 7.82 reject gravel – 0.08 1.78 0.35 5.16 m 7.29 shingle 40mm aggregate – 0.08 1.78 0.35 6.45 m 8.58 sharp sand 6.76 0.08 1.78 0.35 6.76 m 8.89

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Excavating trenches; using 3 tonne tracked excavator; to receive pipes; grading bottoms; earthwork support; filling with imported granular material type 2 and compacting; disposal of surplus soil Services not exceeding 200mm nominal size

average depth of run not exceeding 0.50m 2.59 0.09 2.06 0.72 8.14 m 10.92 average depth of run not exceeding 0.75m 3.89 0.11 2.57 0.90 12.21 m 15.68 average depth of run not exceeding 1.00m 5.18 0.14 3.32 1.18 16.27 m 20.77 average depth of run not exceeding 1.25m 6.48 0.23 5.43 2.02 20.34 m 27.79

Excavating trenches; using 3 tonne tracked excavator; to receive pipes; grading bottoms; earthwork support; filling with concrete, ready mixed ST2; disposal of surplus soil Services not exceeding 200mm nominal size

average depth of run not exceeding 0.50m 12.92 0.11 2.53 0.38 18.47 m 21.38 average depth of run not exceeding 0.75m 19.37 0.13 3.09 0.47 27.69 m 31.25 average depth of run not exceeding 1.00m 25.83 0.17 3.96 0.63 36.92 m 41.51 average depth of run not exceeding 1.25m 32.29 0.23 5.34 0.94 46.15 m 52.43

Earthwork support; providing support to opposing faces of excavation; moving along as work proceeds Maximum depth not exceeding 2.00m

trenchbox; distance between opposing faces not exceeding 2.00m – 0.80 19.00 27.32 – m 46.32 timber; distance between opposing faces not exceeding 500mm – 0.20 9.50 – 0.02 m 9.52

Clay pipes and fittings; Hepworth Plc; Supersleve 100mm clay pipes; polypropylene slip coupling; in trenches (trenches not included)

laid straight 4.52 0.25 5.94 – 6.58 m 12.52 short runs under 3.00m 4.52 0.31 7.42 – 6.58 m 14.00

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

PIPE LAYING – cont

Clay pipes and fittings – cont Extra over 100mm clay pipes for

bends; 15-90°; single socket 9.51 0.25 5.94 – 9.51 nr 15.45 junction; 45 or 90°; double socket 20.05 0.25 5.94 – 20.05 nr 25.99 slip couplings; polypropylene 3.30 0.08 1.98 – 3.30 nr 5.28 gully with P trap; 100mm; 154× 154mm plastic grating 23.15 1.00 23.75 – 38.17 nr 61.92

150mm clay pipes; polypropylene slip coupling; in trenches (trenches not included)

laid straight 14.14 0.30 7.13 – 14.14 m 21.27 short runs under 3.00m 14.14 0.60 14.25 – 14.14 m 28.39

Extra over 150mm clay pipes for bends; 15-90° 11.97 0.28 6.65 – 17.74 nr 24.39 junction; 45 or 90°; 100×150mm 16.02 0.40 9.50 – 27.55 nr 37.05 junction; 45 or 90°; 150×150mm 17.58 0.40 9.50 – 29.12 nr 38.62 slip couplings; polypropylene 5.77 0.05 1.19 – 5.77 nr 6.96 tapered pipe; 100-150mm 18.11 0.50 11.88 – 18.11 nr 29.99 tapered pipe; 150-225mm 46.21 0.50 11.88 – 46.21 nr 58.09 socket adaptor; connection to traditional pipes and fittings 12.14 0.33 7.84 – 17.91 nr 25.75

Accessories in clay access pipe; 150mm 45.12 – – – 56.66 nr 56.66 rodding eye; 150mm 43.16 0.50 11.88 – 48.17 nr 60.05 gully with P traps; 150mm; 154× 154mm plastic grating 50.92 0.80 19.00 – 58.69 nr 77.69

PVC-u pipes and fittings; Wavin Plastics Ltd; OsmaDrain; laid to and covered over with imported granular material 110mm PVC-u pipes; in trenches (trenches not included)

laid straight 5.08 0.08 1.90 1.78 7.22 m 10.90 short runs under 3.00m 5.83 0.12 2.85 1.78 7.97 m 12.60

Extra over 110mm PVC-u pipes for bends; short radius 6.75 0.25 5.94 – 6.75 nr 12.69 bends; long radius 7.22 0.25 5.94 – 7.22 nr 13.16 junctions; equal; double socket 5.34 0.25 5.94 – 5.34 nr 11.28 slip couplings 3.95 0.25 5.94 – 3.95 nr 9.89 adaptors to clay 7.38 0.50 11.88 – 7.38 nr 19.26

160mm PVC-u pipes; in trenches (trenches not included)

laid straight 8.35 0.08 1.90 1.78 10.50 m 14.18 short runs under 3.00m 14.86 0.12 2.85 1.78 17.01 m 21.64

Extra over 160mm PVC-u pipes for socket bend; double; 90 or 45° 19.91 0.20 4.75 – 19.91 nr 24.66 socket bend; double; 15 or 30° 15.56 0.20 4.75 – 15.56 nr 20.31 socket bend; single; 87.5 or 45° 6.12 0.20 4.75 – 6.12 nr 10.87

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

socket bend; single; 15 or 30° 6.12 0.20 4.75 – 6.12 nr 10.87 bends; short radius 16.13 0.25 5.94 – 22.88 nr 28.82 bends; long radius 32.93 0.25 5.94 – 32.93 nr 38.87 junctions; single 19.97 0.33 7.92 – 19.97 nr 27.89 pipe coupler 8.06 0.05 1.19 – 8.06 nr 9.25 slip couplings PVC-u 1.87 0.05 1.19 – 1.87 nr 3.06 adaptors to clay 7.75 0.50 11.88 – 7.75 nr 19.63 level invert reducer 4.72 0.50 11.88 – 4.72 nr 16.60 spiggot 11.78 0.20 4.75 – 11.78 nr 16.53

CATCHWATER OR FRENCH DRAINS

Catchwater or French drains; laying pipes to drain excavated separately; 100mm diameter non-coilable perforated plastic pipes; including straight jointing; pipes laid with perforations uppermost; lining trench; wrapping pipes with filter fabric; backfilling with shingle Width 300mm

depth 450mm 197.44 9.10 216.13 38.88 711.36 100m 966.37 depth 600mm 201.56 9.84 233.70 60.73 899.75 100m 1194.18 depth 750mm 205.86 10.60 251.75 76.98 1088.33 100m 1417.06 depth 900mm 210.07 11.34 269.32 92.81 1276.82 100m 1638.95 depth 1000mm 212.88 11.84 281.20 103.50 1402.48 100m 1787.18 depth 1200mm 218.49 12.84 304.95 124.89 1653.79 100m 2083.63

Width 450mm depth 450mm 203.76 10.44 247.95 112.06 994.09 100m 1354.10 depth 600mm 210.07 11.34 269.32 92.81 1276.82 100m 1638.95 depth 750mm 216.38 12.46 295.93 116.76 1559.54 100m 1972.23 depth 900mm 222.70 13.60 323.00 141.14 1842.27 100m 2306.41 depth 1000mm 226.91 14.34 340.57 156.96 2030.75 100m 2528.28 depth 1200mm 235.33 15.84 376.20 189.04 2407.72 100m 2972.96 depth 1500mm 247.95 18.10 429.88 237.37 2973.18 100m 3640.43 depth 2000mm 269.00 21.84 518.70 317.35 3915.60 100m 4751.65

Width 600mm depth 450mm 210.07 11.24 266.95 92.81 1276.82 100m 1636.58 depth 600mm 218.49 12.84 304.95 124.89 1653.79 100m 2083.63 depth 750mm 226.91 14.34 340.57 156.96 2030.75 100m 2528.28 depth 900mm 235.33 15.84 376.20 189.04 2407.72 100m 2972.96 depth 1000mm 232.54 16.84 399.95 210.43 2650.64 100m 3261.02 depth 1200mm 252.16 18.84 447.45 253.19 3161.66 100m 3862.30 depth 1500mm 269.00 21.84 518.70 746.35 3915.60 100m 5180.65 depth 2000mm 297.06 19.84 471.20 573.97 5172.16 100m 6217.33

Width 900mm depth 450mm 200.72 13.60 323.00 141.14 1820.29 100m 2284.43 depth 600mm 235.33 7.92 188.10 189.04 2407.72 100m 2784.86 depth 750mm 247.95 9.05 214.94 237.37 2973.18 100m 3425.49

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

CATCHWATER OR FRENCH DRAINS – cont

Catchwater or French drains – cont Width 900mm – cont

depth 900mm 260.58 10.17 241.54 285.27 3538.63 100m 4065.44 depth 1000mm 269.00 10.92 259.35 317.35 3915.60 100m 4492.30 depth 1200mm 285.84 12.42 294.98 381.50 4669.54 100m 5346.02 depth 1500mm 311.09 14.67 348.41 477.73 5800.44 100m 6626.58 depth 2000mm 353.19 18.92 449.35 781.12 7685.28 100m 8915.75 depth 2500mm 395.28 22.17 526.54 941.51 9570.13 100m 11038.18 depth 3000mm 437.37 25.92 615.60 958.89 11454.97 100m 13029.46

Catchwater or French drains; laying pipes to drains excavated separately; 160mm diameter non-coilable perforated plastic pipes; including straight jointing; pipes laid with perforations uppermost; lining trench; wrapping pipes with filter fabric; backfilling with shingle Width 600mm

depth 450mm 393.30 11.20 266.00 89.82 1426.47 100m 1782.29 depth 600mm 401.72 12.70 301.63 121.89 1803.43 100m 2226.95 depth 750mm 410.13 14.20 337.25 153.97 2180.40 100m 2671.62 depth 900mm 418.55 15.70 372.88 186.05 2557.37 100m 3116.30 depth 1000mm 424.17 16.70 396.63 207.43 2808.68 100m 3412.74 depth 1200mm 435.39 18.70 444.13 250.33 3311.31 100m 4005.77 depth 1500mm 452.23 21.70 515.38 314.36 4065.25 100m 4894.99 depth 2000mm 480.29 26.70 634.13 421.28 5321.81 100m 6377.22 depth 2500mm 508.35 31.70 752.88 528.20 6578.37 100m 7859.45 depth 3000mm 536.42 36.70 871.63 635.13 7834.93 100m 9341.69

Width 900mm depth 450mm 200.72 13.60 323.00 141.14 1820.29 100m 2284.43 depth 600mm 213.35 15.84 376.20 189.04 2385.74 100m 2950.98 depth 750mm 225.98 18.10 429.88 237.37 2951.20 100m 3618.45 depth 900mm 238.60 20.34 483.07 285.27 3516.65 100m 4284.99 depth 1000mm 247.02 21.84 518.70 317.35 3893.62 100m 4729.67 depth 1200mm 263.86 24.84 589.95 381.50 4647.56 100m 5619.01 depth 1500mm 289.12 29.34 696.83 477.73 5778.46 100m 6953.02 depth 2000mm 331.21 36.84 874.95 638.12 7663.31 100m 9176.38 depth 2500mm 373.30 44.34 1053.08 798.51 9548.15 100m 11399.74 depth 3000mm 415.40 51.84 1231.20 958.89 11432.99 100m 13623.08

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

DITCHING

Ditching; clear silt and bottom ditch not exceeding 1.50m deep; strim back vegetation; disposing to spoil heaps; by machine Up to 1.50m wide at top – 6.00 142.50 28.13 – 100m 170.63 1.50-2.50m wide at top – 8.00 190.00 37.50 – 100m 227.50 2.50-4.00m wide at top – 9.00 213.75 42.19 – 100m 255.94

Ditching; clear only vegetation from ditch not exceeding 1.50m deep; disposing to spoil heaps; by strimmer Up to 1.50m wide at top – 5.00 118.75 7.15 – 100m 125.90 1.50-2.50m wide at top – 6.00 142.50 12.87 – 100m 155.37 2.50-4.00m wide at top – 7.00 166.25 20.02 – 100m 186.27

Ditching; clear silt from ditch not exceeding 1.50m deep; trimming back vegetation; disposing to spoil heaps; by hand Up to 1.50m wide at top – 15.00 356.25 7.15 – 100m 363.40 1.50-2.50m wide at top – 27.00 641.25 12.87 – 100m 654.12 2.50-4.00m wide at top – 42.00 997.50 20.02 – 100m 1017.52

Ditching; excavating and forming ditch and bank to given profile (normally 45°); in loam or sandy loam; by machine Width 300mm

depth 600mm – 3.70 87.88 34.69 – 100m 122.57 depth 900mm – 5.20 123.50 48.75 – 100m 172.25 depth 1200mm – 7.20 171.00 67.50 – 100m 238.50 depth 1500mm – 9.40 223.25 77.11 – 100m 300.36

Width 600mm depth 600mm – – – 101.23 – 100m 101.23 depth 900mm – – – 150.22 – 100m 150.22 depth 1200mm – – – 204.10 – 100m 204.10 depth 1500mm – – – 293.91 – 100m 293.91

Width 900mm depth 600mm – – – 481.43 – 100m 481.43 depth 900mm – – – 848.23 – 100m 848.23 depth 1200mm – – – 1139.83 – 100m 1139.83 depth 1500mm – – – 1412.18 – 100m 1412.18

Width 1200mm depth 600mm – – – 756.52 – 100m 756.52 depth 900mm – – – 1123.33 – 100m 1123.33 depth 1200mm – – – 1487.83 – 100m 1487.83 depth 1500mm – – – 1906.44 – 100m 1906.44

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

DITCHING – cont

Ditching – cont Width 1500mm

depth 600mm – – – 933.05 – 100m 933.05 depth 900mm – – – 1422.27 – 100m 1422.27 depth 1200mm – – – 1891.31 – 100m 1891.31 depth 1500mm – – – 2370.45 – 100m 2370.45

Extra for ditching in clay – – – – – 20% –

Ditching; excavating and forming ditch and bank to given profile (normal 45°); in loam or sandy loam; by hand Width 300mm

depth 600mm – 36.00 855.00 – – 100m 855.00 depth 900mm – 42.00 997.50 – – 100m 997.50 depth 1200mm – 56.00 1330.00 – – 100m 1330.00 depth 1500mm – 70.00 1662.50 – – 100m 1662.50

Width 600mm depth 600mm – 56.00 1330.00 – – 100m 1330.00 depth 900mm – 84.00 1995.00 – – 100m 1995.00 depth 1200mm – 112.00 2660.00 – – 100m 2660.00 depth 1500mm – 140.00 3325.00 – – 100m 3325.00

Width 900mm depth 600mm – 84.00 1995.00 – – 100m 1995.00 depth 900mm – 126.00 2992.50 – – 100m 2992.50 depth 1200mm – 168.00 3990.00 – – 100m 3990.00 depth 1500mm – 210.00 4987.50 – – 100m 4987.50

Width 1200mm depth 600mm – 112.00 2660.00 – – 100m 2660.00 depth 900mm – 168.00 3990.00 – – 100m 3990.00 depth 1200mm – 224.00 5320.00 – – 100m 5320.00 depth 1500mm – 280.00 6650.00 – – 100m 6650.00

Extra for ditching in clay – – – – – 50% – Extra for ditching in compacted soil – – – – – 90% –

Piped ditching Jointed concrete pipes; FP McCann Ltd; including bedding, haunching and topping with 150mm concrete; 11.50N/mm2 – 40mm aggregate; to existing ditch

300mm diameter 21.84 0.67 15.83 10.09 42.82 m 68.74 450mm diameter 32.55 0.67 15.83 10.09 64.03 m 89.95 600mm diameter 52.29 0.67 15.83 10.09 96.98 m 122.90 900mm diameter 138.60 1.00 23.75 15.13 162.29 m 201.17

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Jointed concrete pipes; FP McCann Ltd; including bedding, haunching and topping with 150mm concrete; 11.50N/mm2 – 40mm aggregate; to existing ditch

1200mm diameter 237.87 1.00 23.75 15.13 268.87 m 307.75 extra over jointed concrete pipes for bends to 45° 218.40 0.67 15.83 12.61 227.85 nr 256.29 extra over jointed concrete pipes for single junctions 300mm diameter 149.63 0.67 15.83 12.61 159.08 nr 187.52 extra over jointed concrete pipes for single junctions 450mm diameter 221.81 0.67 15.83 11.46 231.26 nr 258.55 extra over jointed concrete pipes for single junctions 600mm diameter 359.52 0.67 15.83 11.46 368.97 nr 396.26 extra over jointed concrete pipes for single junctions 900mm diameter 607.74 0.67 15.83 11.46 617.19 nr 644.48 extra over jointed concrete pipes for single junctions 1200mm diameter 928.41 0.67 15.83 11.46 937.86 nr 965.15

Outfalls Reinforced concrete outfalls to water course; flank walls; for 150mm drain outlets; overall dimensions

Small headwall FP McCann Ltd 638.60 4.00 285.00 46.59 701.00 m 1032.59

LAND DRAINS

Market prices of backfilling materials Sand 41.40 – – – 41.40 m3 41.40 Gravel rejects 36.02 – – – 36.02 m3 36.02 Imported topsoil (allowing for 20% settlement) – – – – 39.60 m3 39.60

Land drainage; calculation table For calculation of drainage per hectare the following table can be used; rates show the lengths of drains per unit and not the value Lateral drains

10.00m centres – – – – – m/ha 1000.00 15.00m centres – – – – – m/ha 650.00 25.00m centres – – – – – m/ha 400.00 30.00m centres – – – – – m/ha 330.00

Main drains 1 nr (at 100m centres) – – – – – m/ha 100.00 2 nr (at 50m centres) – – – – – m/ha 200.00 3 nr (at 33.3m centres) – – – – – m/ha 300.00 4 nr (at 25m centres) – – – – – m/ha 400.00

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

LAND DRAINS – cont

Land drainage; excavating Removing 150mm depth of topsoil; 300mm wide; depositing beside trench; by machine – 1.50 35.63 14.06 – 100m 49.69 Removing 150mm depth of topsoil; 300mm wide; depositing beside trench; by hand – 8.00 190.00 – – 100m 190.00

Excavated material; disposal on site In spoil heaps

average 25m distance – – – 2.44 – m3 2.44 average 50m distance – – – 2.82 – m3 2.82 average 100m distance (1 dumper) – – – 3.53 – m3 3.53 average 100m distance (2 dumpers) – – – 4.22 – m3 4.22 average 200m distance – – – 4.26 – m3 4.26 average 200m distance (2 dumpers) – – – 5.08 – m3 5.08

Removing excavated material from site to tip; mechanically loaded

excavated material and clean hardcore rubble – – – 1.91 29.20 m3 31.11

Land drainage; Agripower Ltd; excavating trenches (with minimum project size of 1000m) by trenching machine; spreading arisings on site; laying perforated pipe; as shown below; backfilling with shingle to 350mm from surface Width 150mm; 80mm perforated pipe

depth 750mm – – – – – m 6.64 Width 175mm; 100mm perforated pipe

depth 800mm – – – – – m 7.05 Width 250mm; 150mm perforated pipe

depth 900mm – – – – – m 10.28

Land drainage; excavating for drains; by 5 tonne mini-excavator; including disposing spoil to spoil heaps not exceeding 100m; boning to levels by laser Width 150-225mm

depth 450mm – 9.67 229.58 330.13 – 100m 559.71 depth 600mm – 13.00 308.75 495.19 – 100m 803.94 depth 700mm – 15.50 368.13 618.99 – 100m 987.12 depth 900mm – 23.00 546.25 990.39 – 100m 1536.64

Width 300mm depth 450mm – 9.67 229.58 330.13 – 100m 559.71 depth 700mm – 14.00 332.50 544.71 – 100m 877.21 depth 900mm – 23.00 546.25 990.39 – 100m 1536.64

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

depth 1000mm – 25.00 593.75 1089.43 – 100m 1683.18 depth 1200mm – 25.00 593.75 1237.99 – 100m 1831.74 depth 1500mm – 31.00 736.25 1386.54 – 100m 2122.79

Land drainage; excavating for drains; by 7 tonne tracked excavator; including disposing spoil to spoil heaps not exceeding 100m Width 225mm

depth 450mm – 7.00 166.25 92.31 – 100m 258.56 depth 600mm – 7.17 170.21 96.16 – 100m 266.37 depth 700mm – 7.35 174.51 100.34 – 100m 274.85 depth 900mm – 7.76 184.35 109.90 – 100m 294.25 depth 1000mm – 8.00 190.00 115.39 – 100m 305.39 depth 1200mm – 8.26 196.25 121.46 – 100m 317.71

Width 300mm depth 450mm – 7.35 174.51 100.34 – 100m 274.85 depth 600mm – 7.76 184.35 109.90 – 100m 294.25 depth 700mm – 8.26 196.25 121.46 – 100m 317.71 depth 900mm – 9.25 219.69 144.24 – 100m 363.93 depth 1000mm – 10.14 240.89 164.85 – 100m 405.74 depth 1200mm – 11.00 261.25 184.63 – 100m 445.88

Width 600mm depth 450mm – 13.00 308.75 230.78 – 100m 539.53 depth 600mm – 14.11 335.14 256.42 – 100m 591.56 depth 700mm – 16.33 387.92 307.71 – 100m 695.63 depth 900mm – 17.29 410.54 329.69 – 100m 740.23 depth 1000mm – 18.38 436.63 355.05 – 100m 791.68 depth 1200mm – 21.18 503.07 419.60 – 100m 922.67

Land drainage; excavating for drains; by hand, including disposing spoil to spoil heaps not exceeding 100m Width 150mm

depth 450mm – 0.44 10.46 – – m 10.46 depth 600mm – 0.59 13.96 – – m 13.96 depth 700mm – 0.69 16.27 – – m 16.27 depth 900mm – 0.88 20.93 – – m 20.93

Width 225mm depth 450mm – 0.66 15.70 – – m 15.70 depth 600mm – 0.88 20.93 – – m 20.93 depth 700mm – 1.03 24.42 – – m 24.42 depth 900mm – 1.32 31.40 – – m 31.40

Width 300mm depth 450mm – 0.88 20.93 – – m 20.93 depth 600mm – 1.18 27.91 – – m 27.91 depth 700mm – 1.37 32.56 – – m 32.56

Width 375mm depth 450mm – 1.10 26.16 – – m 26.16 depth 600mm – 1.47 34.88 – – m 34.88 depth 700mm – 1.71 40.70 – – m 40.70

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

LAND DRAINS – cont

Land drainage; pipe laying

Wavin Plastics Ltd; flexible plastic perforated pipes in trenches (not included); to a minimum depth of 450mm (couplings not included) OsmaDrain; flexible plastic perforated pipes in trenches (not included); to a minimum depth of 450mm (couplings not included)

80mm diameter; available in 100m coil 86.10 2.00 47.50 – 86.10 100m 133.60 100mm diameter; available in 100m coil 138.58 2.00 47.50 – 138.58 100m 186.08 160mm diameter; available in 35m coil 334.97 2.00 47.50 – 334.97 100m 382.47

WavinCoil; plastic pipe junctions 100× 80mm 4.01 0.05 1.19 – 4.01 nr 5.20 160× 160mm 10.00 0.05 1.19 – 10.00 nr 11.19

WavinCoil; couplings for flexible pipes 100mm diameter 1.47 0.03 0.79 – 1.47 nr 2.26 160mm diameter 1.98 0.03 0.79 – 1.98 nr 2.77

Land drainage; backfilling trench after laying pipes with gravel rejects or similar; blind filling with ash or sand; topping with 150mm imported topsoil from dumps not exceeding 100m; by machine Width 150mm

depth 450mm – 3.30 78.38 81.37 231.05 100m 390.80 depth 600mm – 4.30 102.13 106.59 310.95 100m 519.67 depth 900mm – 6.30 149.63 157.02 452.11 100m 758.76

Width 225mm depth 600mm – 6.45 153.19 159.88 466.60 100m 779.67 depth 900mm – 9.45 224.44 235.54 687.66 100m 1147.64

Land drainage; backfilling trench after laying pipes with gravel rejects or similar, blind filling with ash or sand; topping with 150mm topsoil from dumps not exceeding 100m; by hand Width 150mm

depth 450mm – 0.18 4.28 – 2.15 m 6.43 depth 600mm – 24.84 589.95 – 310.95 100m 900.90 depth 750mm – 31.05 737.44 – 279.62 100m 1017.06 depth 900mm – 37.26 884.92 – 452.11 100m 1337.03

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

Width 225mm depth 450mm – 27.94 663.58 – 356.23 100m 1019.81 depth 600mm – 37.26 884.92 – 466.60 100m 1351.52 depth 750mm – 46.57 1106.04 – 577.29 100m 1683.33 depth 900mm – 55.89 1327.39 – 687.66 100m 2015.05

Width 375mm depth 450mm – 46.57 1106.04 – 593.49 100m 1699.53 depth 600mm – 61.10 1451.13 – 777.55 100m 2228.68 depth 750mm – 77.63 1843.71 – 961.93 100m 2805.64 depth 900mm – 93.15 2212.31 – 1145.99 100m 3358.30

MARKET PRICES OF BACKFILLING MATERIALS

Market prices of commonly used materials used for backfilling The prices below show the market price with standard settlement factors allowed for

Sharp sand – – – – 43.00 m3 43.00 Gravel (washed river or pit) – – – – 39.77 m3 39.77 Shingle – – – – 45.66 m3 45.66 Topsoil – – – – 39.60 m3 39.60 Gravel rejects – – – – 33.57 m3 33.57 Selected granular material 6F2 – – – – 14.40 m3 14.40

SAND SLITTING/GROOVING

Sand slitting; Agripower Ltd Drainage slits; at 1.00m centres; using spinning disc trenching machine; backfilling to 100mm of surface with pea gravel; finished surface with medium grade sand 100; arisings to be loaded, hauled and tipped on site; minimum pitch size 6000m2

250mm depth – – – – – m 2.05 300mm depth – – – – – m 2.25 400mm depth – – – – – m 3.38

Sand grooving or banding; Agripower Ltd Drainage bands at 260mm m centres; using Blec Sandmaster; to existing grass at 260mm centres; minimum pitch size 4000m2

sand banding or sand grooving – – – – – m2 1.14

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

SOAKAWAYS

Preamble: Flat rate hourly rainfall = 50mm/hr and assumes 100 impermeability of the run-off area. A storage capacity of the soakaway should be ⅓ of the hourly rainfall. Formulae for calculating soakaway depths are provided in the publications mentioned below and in the Tables and Memoranda section of this publication. The design of soakaways is dependent on, amongst other factors, soil conditions, permeability, groundwater level and runoff. The definitive documents for design of soakaways are CIRIA 156 and BRE Digest 365 dated September 1991. The suppliers of the systems below will assist through their technical divisions. Excavation earthwork support of pits and disposal not included.