ABSTRACT

Total Gang Rate/Hour 1.00 85.62 – – - 85.62

RESOURCES – PLANT Clearance

0.8m3 tractor loader – 50% of time – – 21.75 – - 21.75 8 t lorry with hiab – 25% of time – – 7.14 – - 7.14 4 t dumper – 50% of time – – 7.49 – - 7.49 20 t mobile crane – 25% of time – – 37.74 – - 37.74 compressor, 11.3m3/min (450 cfm), 4 tool – – 21.31 – - 21.31 compressor tools: two brick hammers/picks – 50% of time – – 1.58 – - 1.58 compressor tools: chipping hammer – – 0.70 – - 0.70 compressor tools: medium rock drill 30 – – 0.84 – - 0.84 compressor tools: road breaker – – 2.30 – - 2.30 compressor tools: two 15m lengths hose – – 0.33 – - 0.33

Total Rate/Hour – – 101.18 – - 101.18

SITE CLEARANCE General site clearance

open field site 9.91 848.51 997.36 – ha 1845.87 medium density wooded 20.61 1764.67 2073.91 – ha 3838.58 heavy density wooded 32.09 2747.61 3229.18 – ha 5976.79 urban areas (town centre) 30.60 2620.03 3079.55 – ha 5699.58 live dual carriageway 30.60 2620.03 3079.55 – ha 5699.58

hours £ £ £ rate £

SITE CLEARANCE – cont Demolition of building or structure

building; brick construction with timber floor and roof – – – – m3 7.67 building; brick construction with concrete floor and roof – – – – m3 13.50 building; masonry construction with timber floor and roof – – – – m3 9.96 building; reinforced concrete frame construction with brick infill – – – – m3 13.24 building; steel frame construction with brick infill – – – – m3 7.20 building; steel frame construction with cladding – – – – m3 6.87 building; timber – – – – m3 6.20 reinforced concrete bridge deck or superstructure – – – – m3 62.44 reinforced concrete bridge abutment or bank seat – – – – m3 56.76 reinforced concrete retaining wall – – – – m3 170.29 brick or masonry retaining wall – – – – m3 95.93 brick or masonry boundary wall – – – – m3 79.46 dry stone boundary wall – – – – m3 85.14

TAKE UP OR TAKE DOWN AND SET ASIDE FOR RE-USE OR REMOVE TO STORE OR TIP OFF SITE Take up or down and set aside for re-use

precast concrete kerbs and channels 0.02 1.46 3.30 – m 4.76 precast concrete edgings 0.01 1.10 2.58 – m 3.68 precast concrete drainage and kerb blocks 0.02 1.82 4.05 – m 5.87 precast concrete drainage channel systems 0.02 1.82 4.05 – m 5.87 tensioned single sided corrugated beam safety fence 0.14 11.99 14.23 – m 26.22 timber post and 4 rail fence 0.08 6.85 8.09 – m 14.94 bench seat 0.13 11.13 11.14 – nr 22.27 cattle trough 0.16 13.36 13.31 – nr 26.67 permanent bollard 0.13 11.13 11.14 – nr 22.27 pedestrian crossing lights; pair 0.26 22.26 26.38 – nr 48.64 lighting column including bracket arm and lantern; 5m high 0.58 49.66 58.75 – nr 108.41 lighting column including bracket arm and lantern; 10m high 0.61 52.23 61.69 – nr 113.92 traffic sign 0.26 22.26 26.38 – nr 48.64 timber gate 0.13 11.13 11.14 – nr 22.27 stile 0.13 11.13 11.14 – nr 22.27 road stud 0.03 2.23 2.18 – nr 4.41 chamber cover and frame 0.03 2.23 2.18 – nr 4.41 gully grating and frame 0.03 2.23 2.18 – nr 4.41 feeder pillars 0.03 2.23 2.18 – nr 4.41

hours £ £ £ rate £

Take up or down and remove to store off site precast concrete kerbs and channels 0.02 1.46 5.44 – m 6.90 precast concrete edgings 0.01 1.10 4.19 – m 5.29 precast concrete drainage and kerb blocks 0.02 1.82 6.72 – m 8.54 precast concrete drainage channel systems 0.02 1.82 6.72 – m 8.54 tensioned single sided corrugated beam safety fence 0.14 11.99 16.00 – m 27.99 timber post and 4 rail fence 0.08 6.85 9.10 – m 15.95 bench seat 0.13 11.13 17.69 – nr 28.82 cattle trough 0.16 13.36 21.18 – nr 34.54 permanent bollard 0.13 11.13 17.69 – nr 28.82 pedestrian crossing lights; pair 0.26 22.26 29.65 – nr 51.91 lighting column including bracket arm and lantern; 5m high 0.58 49.66 66.06 – nr 115.72 lighting column including bracket arm and lantern; 10m high 0.61 52.23 69.38 – nr 121.61 traffic sign 0.26 22.26 29.65 – nr 51.91 timber gate 0.13 11.13 17.69 – nr 28.82 stile 0.13 11.13 17.69 – nr 28.82 road stud 0.03 2.23 3.49 – nr 5.72 chamber cover and frame 0.03 2.23 3.49 – nr 5.72 gully grating and frame 0.03 2.23 3.49 – nr 5.72 feeder pillars 0.03 2.23 3.49 – nr 5.72

Take up or down and remove to tip off site tensioned single sided corrugated beam safety fence 0.17 14.56 17.08 – m 31.64 timber post and 4 rail fence 0.09 7.71 9.03 – m 16.74 low pressure gas mains up to 150mm diameter 0.04 3.42 4.02 – m 7.44 low pressure water mains up to 75mm diameter 0.03 2.57 3.06 – m 5.63 power cable laid singly 0.03 2.57 3.06 – m 5.63 lighting column including bracket arm and lantern; 5m high 0.82 70.21 82.58 – nr 152.79 lighting column including bracket arm and lantern; 10m high 0.85 72.78 85.49 – nr 158.27 traffic sign including posts 0.38 32.54 37.86 – nr 70.40

Removal of existing reflectorised thermoplastic road markings

100mm wide line – – – – m 1.45 150mm wide line – – – – m 2.14 200mm wide line – – – – m 2.89 arrow or letter ne 6.0m long – – – – nr 21.48 arrow or letter 6.0-16.0m long – – – – nr 89.96