ABSTRACT

For a run-of-river hydroelectric power plant, the intake, along with the diversion, river training, and flood protection works, need to be designed for the following conditions:

i. It should be possible to divert the design flow into the intake when there is sufficient discharge in the river-that is, when the available river discharge less the environmental release is equal to or larger than the design flow.