ABSTRACT
RESOURCESLABOUR
Formwork gang-small areas
1 foreman joiner (craftsman)
15.46
1 joiner (craftsman)
14.71
1 unskilled operative (general)
9.52
1 plant operator (craftsman)—50% of time
7.92
Total Gang Rate/Hour
£ 47.61
Formwork gang-large areas
1 foreman joiner (craftsman)
15.46
2 joiners (craftsman)
29.42
1 unskilled operative (general)
9.52
1 plant operator (craftsman)—25% of time
3.96
Total Gang Rate/Hour
£ 58.36
Reinforcement gang
1 foreman steel fixer (craftsman)
15.46
4 steel fixers (craftsman)
58.84
1 unskilled operative (general)
9.52
1 plant operator (craftsman)—25%
3.96
Rate/Hour
Reinforcementon-site bending/baling gang
1 steel fixer (craftsman)
14.71
1 unskilled operative (general)
9.52
1 plant operator (craftsman)—25% of time
3.96
Total Gang Rate/Hour
£ 28.19
Joints gang 1 ganger/chargehand (skill rate 4)
10.16
1 skilled operative (skill rate 4)
10.16
1 unskilled operative (general)
9.52
Total Gang Rate/Hour
£ 29.84
Concrete accessories gang
1 ganger/chargehand (skill rate 4)
10.16
1 skilled operative (skill rate 4)
10.16
1 unskilled operative (general)
9.52
Total Gang Rate/Hour
£ 29.84
RESOURCESPLANT
Formworksmall areas
20 t crawler crane-50% of time
9.41
22“diameter saw bench
1.19
allowance for small power tools
1.78
large areas
20 t crawler crane-25% of time
4.70
22″ diameter saw bench
1.19
allowance for small power tools
1.78
Total Rate/Hour £ 7.68 Reinforcement 30 t crawler crane-25% of time
6.10
bar cropper 2.09 small power tools 0.58 support acrows, tirfors, kentledge, etc.