ABSTRACT

Cutting off surplus lengths

mass 30-60 kg/m – – – – nr 4.67 mass 60-120 kg/m – – – – nr 7.01 mass 120-250 kg/m

– – – – nr 9.35

Burning off tops of piles to level

mass 30-60 kg/m – – – – nr 4.67 mass 60-120 kg/m – – – – nr 7.01 mass 120-250 kg/m

– – – – nr 9.35

INTERLOCKING STEEL PILES

Frodingham Steel bearing piles are commonly carried out by a Specialist Contractor and

arrive at accurate costing. However the following items can be used to assess a budget cost for such work. The item for number of pile extensions includes for welding the extension to the top of the steel bearing pile. The items for length of pile extension cover the material only, the driving cost being included in Class P.