ABSTRACT
RESOURCESLABOUR
Drain repair gang 1 chargehand pipelayer (skill rate 4)—50% of time
5.33
1 skilled operative (skill rate 4)
10.16
2 unskilled operatives (generally)
19.04
1 plant operator (skill rate 3)
12.38
Total Gang Rate/Hour
£ 46.91
RESOURCESPLANT
Drainage 0.40 m3 hydraulic excavator
15.20
trench sheets, shores, props etc.