ABSTRACT
Sub-base laying gang
1 ganger/chargehand (skill rate 4)
10.30
1 skilled operative (skill rate 4)
10.16
2 unskilled operatives (general)
19.04
1 plant operator (skill rate 2)
13.81
1 plant operator (skill rate 3)
12.38
Total Gang Rate/Hour
£ 66.05
Flexible paving gang
1 ganger/chargehand (skill rate 4)
10.66
2 skilled operatives (skill rate 4)
20.32
4 unskilled operatives (general)
38.08
4 plant operators (skill rate 3)
49.52
Total Gang Rate/Hour
£ 118.58
Concrete paving gang
1 ganger/chargehand (skill rate 4)
10.66
2 skilled operatives (skill rate 4)
20.32
4 unskilled operatives (general)
38.08
1 plant operator (skill rate 2)
13.81
1 plant operator (skill rate 3)
12.38
Total Rate/Hour £ 95.25
1 plant operator (skill rate 3)
12.38
Total Gang Cost/Hour
£ 12.38
Road chippings gang
1 ganger/chargehand (skill rate 4)—50% of time
5.33
1 skilled operative (skill rate 4)
10.16
2 unskilled operatives (general)
19.04
3 plant operators (skill rate 3)
37.14
Total Gang Rate/Hour
£ 71.67
Cutting slabs gang 1 unskilled operative (general)
9.52
Total Gang Rate/Hour
£ 9.52
Concrete filled joints gang
1 ganger/chargehand50% of time
5.33
1 skilled operative (skill rate 4)
10.16
2 unskilled operatives (general)
19.04
Total Gang Rate/Hour
£ 34.53
Milling gang 1 ganger/chargehand (skill rate 4)
10.66
2 skilled operatives (skill rate 4)
20.32
4 unskilled operatives (general)
38.08
1 plant operator (skill rate 2)
13.81
1 plant operator (skill rate 3)
12.38
Total Gang Rate/Hour
£ 95.25
gang
1 ganger/chargehand (skill rate 4)
10.66
1 skilled operative (skill rate 4)
10.16
3 unskilled operatives (general)
28.56
1 plant operator (skill rate 4)
11.08
1 plant operator (skill rate 3)
12.38
Total Gang Rate/Hour
£ 72.84
RESOURCESPLANT
Sub-base laying 93 kW motor grader
19.41
0.8 m3 tractor loader
16.67
6 t towed vibratory roller
7.43
Total Gang Rate/Hour
£ 43.51
Flexible paving 2 asphalt pavers, 35 kW, 4.0 m
77.96
2 deadweight rollers, 3 point, 10 t
22.94
tractor with front bucket and integral 2 tool compressor
14.41
compressor tools: rammer
0.37
compressor tools: poker vibrator
1.31
compressor tools: extra 15 m hose
0.23
tar sprayer, 100 2.79
chip spreader
channel (heat) iron
1.02
Total Gang Rate/Hour
£ 127.96
Concrete paving wheeled loader, 2.60 m3
44.77
concrete paver, 6.0 m
63.25
concrete slipform finisher
14.46
Total Gang Rate/Hour
£ 122.48
Road surface spraying
tar sprayer; 100 litre
2.79
Total Gang Rate/Hour
£ 2.79
Road chippings deadweight roller, 3 point, 10 t
11.47
tar sprayer, 100 litre
2.79
self propelled chip spreader
6.92
channel (heat) iron
1.02
Total Gang Rate/Hour
£ 22.20
Cutting slabs compressor, 65 cfm
3.15
12“disc cutter 1.57 Total Gang Rate/Hour
4.72
100 mm deep £ 16.49 Cold milling cold planer, 2.10 m
45.19
wheeled loader, 2.60 m3
44.77
Total Gang Rate/Hour
£ 89.96
m
wheeled loader, 2.60 m3
44.77
Total Gang Rate/Hour
£ 110.92
Rake and compact planed material
deadweight roller, 3 point, 10 t
11.47
tractor with front bucket and integral 2 tool compressor
14.41
channel (heat) iron
1.02
Total Gang Rate/Hour
£ 26.91
SUB-BASE The following unit costs are generally based on the Department of Transport (DTp) Specification for Highway Works and reference is made throughout this Section to clauses within that specification.