ABSTRACT

Sub-base laying gang

1 ganger/chargehand (skill rate 4)

10.30

1 skilled operative (skill rate 4)

10.16

2 unskilled operatives (general)

19.04

1 plant operator (skill rate 2)

13.81

1 plant operator (skill rate 3)

12.38

Total Gang Rate/Hour

£ 66.05

Flexible paving gang

1 ganger/chargehand (skill rate 4)

10.66

2 skilled operatives (skill rate 4)

20.32

4 unskilled operatives (general)

38.08

4 plant operators (skill rate 3)

49.52

Total Gang Rate/Hour

£ 118.58

Concrete paving gang

1 ganger/chargehand (skill rate 4)

10.66

2 skilled operatives (skill rate 4)

20.32

4 unskilled operatives (general)

38.08

1 plant operator (skill rate 2)

13.81

1 plant operator (skill rate 3)

12.38

Total Rate/Hour £ 95.25

1 plant operator (skill rate 3)

12.38

Total Gang Cost/Hour

£ 12.38

Road chippings gang

1 ganger/chargehand (skill rate 4)—50% of time

5.33

1 skilled operative (skill rate 4)

10.16

2 unskilled operatives (general)

19.04

3 plant operators (skill rate 3)

37.14

Total Gang Rate/Hour

£ 71.67

Cutting slabs gang 1 unskilled operative (general)

9.52

Total Gang Rate/Hour

£ 9.52

Concrete filled joints gang

1 ganger/chargehand50% of time

5.33

1 skilled operative (skill rate 4)

10.16

2 unskilled operatives (general)

19.04

Total Gang Rate/Hour

£ 34.53

Milling gang 1 ganger/chargehand (skill rate 4)

10.66

2 skilled operatives (skill rate 4)

20.32

4 unskilled operatives (general)

38.08

1 plant operator (skill rate 2)

13.81

1 plant operator (skill rate 3)

12.38

Total Gang Rate/Hour

£ 95.25

gang

1 ganger/chargehand (skill rate 4)

10.66

1 skilled operative (skill rate 4)

10.16

3 unskilled operatives (general)

28.56

1 plant operator (skill rate 4)

11.08

1 plant operator (skill rate 3)

12.38

Total Gang Rate/Hour

£ 72.84

RESOURCESPLANT

Sub-base laying 93 kW motor grader

19.41

0.8 m3 tractor loader

16.67

6 t towed vibratory roller

7.43

Total Gang Rate/Hour

£ 43.51

Flexible paving 2 asphalt pavers, 35 kW, 4.0 m

77.96

2 deadweight rollers, 3 point, 10 t

22.94

tractor with front bucket and integral 2 tool compressor

14.41

compressor tools: rammer

0.37

compressor tools: poker vibrator

1.31

compressor tools: extra 15 m hose

0.23

tar sprayer, 100 2.79

chip spreader

channel (heat) iron

1.02

Total Gang Rate/Hour

£ 127.96

Concrete paving wheeled loader, 2.60 m3

44.77

concrete paver, 6.0 m

63.25

concrete slipform finisher

14.46

Total Gang Rate/Hour

£ 122.48

Road surface spraying

tar sprayer; 100 litre

2.79

Total Gang Rate/Hour

£ 2.79

Road chippings deadweight roller, 3 point, 10 t

11.47

tar sprayer, 100 litre

2.79

self propelled chip spreader

6.92

channel (heat) iron

1.02

Total Gang Rate/Hour

£ 22.20

Cutting slabs compressor, 65 cfm

3.15

12“disc cutter 1.57 Total Gang Rate/Hour

4.72

100 mm deep £ 16.49 Cold milling cold planer, 2.10 m

45.19

wheeled loader, 2.60 m3

44.77

Total Gang Rate/Hour

£ 89.96

m

wheeled loader, 2.60 m3

44.77

Total Gang Rate/Hour

£ 110.92

Rake and compact planed material

deadweight roller, 3 point, 10 t

11.47

tractor with front bucket and integral 2 tool compressor

14.41

channel (heat) iron

1.02

Total Gang Rate/Hour

£ 26.91

SUB-BASE The following unit costs are generally based on the Department of Transport (DTp) Specification for Highway Works and reference is made throughout this Section to clauses within that specification.