ABSTRACT
Plant not included in unit costs 154,082 1,049,830 Estimated net cost of measured work, priced at unit costs
3,155,000
£ 4,204,830 Allowance for fixed price contract 6% on labour (assumed to be £1,040,000)
62,400
4% on materials (assumed to be £1,650000)
66,000
4% on plant (assumed to be £235,000) 9,400 5% on staff, overheads etc. (assumed to be £230,000)
11,500 149,300
Sub-contractors (net) 1,205,000 Prime cost sums 75,000 Adjustments made at Management Appraisal
price adjustments, add say 75,000 risk evaluation, add say 50,000 125,000 £ 5,759,130 Head office overheads and profit at 9 % 518,321 Finance costs (from two pages earlier) 40,519 Provisional Sums 75,000 Dayworks Bill 75,000 £ 6,467,970