ABSTRACT

Figure Area Perimeter

Rectangle Length×breadth Sum of sides

Triangle Base×half of perpendicular height

Sum of sides

Quadrilateral Sum of areas of contained triangles

Sum of sides

Trapezoidal Sum of areas of contained triangles

Sum of sides

Trapezium perpendicular height

Sum of sides

Parallelogram Base×perpendicular height Sum of sides

Regular polygon Half sum of sides×half internal diameter

Sum of sides

Circle pi×radius2

Figure Surface area Volume

Cylinder pi×2×radius2×length (curved surface only)

Weights of materials kg/m3 kg/m2 kg/m

Aggregate, coarse 1,500

Ashes 800

Ballast 600

Blockboard, standard

Blockboard, tempered 940-1060

Blocks, natural aggregate

75mm 160.00

100mm 215.00

140mm 300.00

Blocks, lighweight aggregate

75mm 60.00

100mm 80.00

140mm 112.00

Bricks, Fletton 1,820.00

Bricks, engineering 2,250.00

Bricks, concrete 1,850.00

Brickwork, 112.5mm 220.00

940-1000

Half of sum of parallel sides×

pi×radius ×length

Diameter ×0.5236

pi×diameter or pi×2×radius

Weights of materials kg/m3 kg/m2 kg/m

Brickwork, 215mm 465.00

Brickwork, 327.5mm 710.00

Cement 1,440

Chalk 2,240

Chipboard, standard 650-750

Chipboard, flooring 680-800

Clay 1,800

Concrete 2,450

6mm 0.091

8mm 0.125

10mm 0.158

12mm 0.191

15mm 0.280

18mm 0.385

22mm 0.531

28mm 0.681

35mm 1.133

42mm 1.368

54mm 1.769

Copper pipes, table Y

6mm 0.117

8mm 0.162

10mm 0.206

12mm 0.251

15mm 0.392

18mm 0.476

22mm 0.697

28mm 0.899

35mm 1.409

42mm 1.700

54mm 2.905

Copper pipes, table Z

6mm 0.077

8mm 0.105

10mm 0.133

12mm 0.161

Copper pipes, table×

Weights of materials kg/m3 kg/m2 kg/m 15mm 0.203 18mm 0.292 22mm 0.359 28mm 0.459 35mm 0.670 42mm 0.922 54mm 1.334

Flint 2,550 Gravel 1,750 Hardcore 1,900 Hoggin 1,750 Glass, clear sheet

3mm 7.50 4mm 10.00 5mm 12.50 6mm 15.00 10mm 25.00 12mm 30.00 15mm 37.50 19mm 47.50 25mm 63.50

Glass, float 3mm 7.50 4mm 10.00 5mm 12.50 6mm 15.00

Glass, patterned 3mm 6.00 4mm 7.50 5mm 9.50 6mm 11.50 10mm 21.50

Laminboard 500-700 Lime, ground 750 Mild steel flat bars

25×9.53mm 1.910 38×9.53mm 2.840 50×12.70 5.060 50×19.00 7.590

Mild steel round bars 6mm 0.222 8mm 0.395 10mm 0.616

Weights of materials kg/m3 kg/m2 kg/m

12mm 0.888

16mm 1.579

20mm 2.466

25mm 3.854

32mm 6.313

40mm 9.864

50mm 15.413

Mild steel square bars

6mm 0.283

8mm 0.503

10mm 0.784

12mm 1.131

16mm 2.010

20mm 3,139

25mm 4.905

32mm 8.035

40mm 12.554

50mm 19.617

Plaster

7.80

Carlite tough coat, 11 mm thick

7.80

Carlite bonding, 8mm thick 7.10

Carlite bonding, 11 mm thick 9.80

Thistle hardwall, 11 mm thick 8.80

Thistle dri-coat, 11 mm thick 8.30

Thistle renovating, 11 mm thick

8.80

Sand 1,600

Screed, 12.5mm thick 29.00

Stone, Bath 2,200

Stone, crushed 1,350

Stone, Darley Dale 2,400

Carlite browning. 11mm thick

Weights of materials kg/m3 kg/m2

Stone, natural 2,400

Stone, Portland 2,200

Stone, reconstructed 2,250

Stone, York 2,400

Terrazzo, 25mm thick 45.50

Timber

Ash 800

Baltic Spruce 480

Beech 815

Birch 720

Box 960

Cedar 480

Ebony 1,215

Elm 625

Greenheart 960

Jarrah 815

Maple 750

Pine, Pitchpine 800

Pine, Red Deal 575

Pine, Yellow Deal 530

Sycamore 530

Teak, African 960

Teak, Indian 655

Walnut 495

Top soil 1,000

Water 950

Woodblock flooring

softwood 12.70

hardwood 17.60

Zinc sheeting 4.6

EXCAVATION AND FILLING Shrinkage of deposited material

Clay −10%

Gravel −7.5%

Sandy soil −12.5%

Bulking excavated material

Clay 40%

Gravel 25%

Sand 20%

Typical fuel comsumption for plant

Engine size kW Litres per hour

Compressors up to 20 4.00 30 6.50 40 8.20 50 9.00 75 16.00 100 20.00 125 25.00 150 30.00

Concrete mixers up to 5 1.00 10 2.40 15 3.80 20 5.00

Dumpers 5 1.30 7 2.00 10 3.00 15 4.00 20 4.90 30 7.00 50 12.00

Excavators 10 2.50 20 4.50 40 9.00 60 13.00 80 17.00

Pumps 5 1.10 10 2.10 15 3.20 20 4.20 25 5.50

CONCRETE WORK Concrete mixes

Mix Cement t Sand m3 Aggregate m3 Water litters

1:1:2 0.50 0.45 0.70 208.00

1:1:5:3 0.37 0.50 0.80 185.00

1:2:4 0.30 0.54 0.85 175.00

1:2:5:5 0.25 0.55 0.85 166.00

1:3:6 0.22 0.55 0.85 160.00

BRICKWORK AND BLOCKWORK

Half brick wall

stretcher bond 59

English bond 89

English garden wall bond 74

Flemish bond 79

One brick wall

English bond 118

Flemish bond 118

One and a half brick wall

English bond 178

Flemish bond 178

Two brick wall

English bond 238

Flemish bond 238

Metric modular bricks

200×100×75mm

90mm thick 133

190mm thick 200

200×100×100mm

90mm thick 50

190mm thick 100

290mm thick 150

300×100×75mm

90mm thick 44

300×100×100mm

90mm thick 50

Blocks per m2 (block size 414×215mm)

60mm thick 9.9

75mm thick 9.9

100mm thick 9.9

140mm thick 9.9

190mm thick 9.9

215mm thick 9.9

Brick size 215×103.5×65mm

half brick wall 0.017 0.024 0.031

one brick wall 0.045 0.059 0.073

one and a half brick wall 0.072 0.093 0.114

two brick wall 0.101 0.128 0.155

Brick size 200×100×75mm Solid m3 Perforated m3

90mm thick 0.016 0.019

190mm thick 0.042 0.048

290mm thick 0.068 0.078

Brick size 200×100×100mm

90mm thick 0.013 0.016

190mm thick 0.036 0.041

290mm thick 0.059 0.067

Brick size 200×100×100mm

90mm thick 0.015 0.018

Block size 440×215mm

60mm thick 0.004

75mm thick 0.005

100mm thick 0.006

140mm thick 0.007

190mm thick 0.008

215mm thick 0.009

MASONRY

Mortar per m2 of random walling m3

300mm thick wall 0.120

450mm thick wall 0.160

550mm thick wall 0.120

CARPENTRY AND JOINERY Length of boarding required m/m2

Board width, 75mm 13.33

Board width, 100mm 10.00

Board width, 125mm 8.00

Board width, 150mm 6.67

Board width, 175mm 5.71

Board width, 200mm 5.00

ROOFING Lap mm Gauge mm Nr/m2 Battens m/m2

Clay/concrete tiles

267×165mm 65 100 60.00 10.00

65 98 64.00 10.50

65 90 68.00 11.30

387×230mm 75 300 16.00 3.20

100 280 17.40 3.50

420×330mm 75 340 10.00 2.90

100 320 10.74 3.10

Fibre slates

500×250mm 90 205 19.50 4.85

80 210 19.10 4.76

70 215 18.60 4.65

600×300mm 105 250 13.60 4.04

100 250 13.40 4.00

90 255 13.10 3.92

80 260 12.90 3.85

70 263 12.70 3.77

400×200mm 70 165 30.00 6.06

75 162 30.90 6.17

90 155 32.30 6.45

500×250mm 70 215 18.60 4.65

75 212 18.90 4.72

90 205 19.50 4.88

100 200 20.00 5.00

110 195 20.50 5.13

600×300mm 100 250 13.4 4.00

110 245 13.60 4.08

Natural slates

405×205mm 75 165 29.59 8.70

405×255mm 75 165 23.75 6.06

405×305mm 75 165 19.00 5.00

460×230mm 75 195 23.00 6.00

460×255mm 75 195 20.37 5.20

460×305mm 75 195 17.00 5.00

510×255mm 75 220 18.02 4.60

510×305mm 75 220 15.00 4.00

560×280mm 75 240 14.81 4.12

560×280mm 75 240 14.00 4.00

610×305mm 75 265 12.27 3.74

Reconstructed stone slates

380×250mm 75 150 16.00 3.20

PLASTERING AND TILING

Plaster coverage m2 per 1000kg

Carlite browning, 11 mm thick 135-155

Carlite tough coat, 11mm thick 135-150

Carlite bonding, 11mm thick 100-115

Thistle hardwall, 11mm thick 115-130

Thistle dri-coat, 11mm thick 135-135

Thistle renovating, 11mm thick 115-125

Tile coverage Nr per m2

43.27

200×200mm 25.00

PLUMBING AND HEATING

Roof drainage Area m2 Pipe mm Gutter mm

One end outlet 15 50 75

38 68 100

100 110 150

Centre outlet 30 50 75

75 68 100

200 110 150

152×152mm

PAINTING AND WALLPAPERING

Average coverage of paints m2 per litre

Timber Plastered surfaces Brickwork

Primer 10-12 9-11 5-7

Undercoat 10-12 11-14 6-8

Gloss 11-14 11-14 6-8

Emulsion 10-12 12-15 6-10

Wallpaper coverage per roll Rolls nr Wall height m Room perimeter m

4 2.50 8

5 2.50 9

5 2.50 10

6 2.50 11

6 2.50 12

7 2.50 13

7 2.50 14

8 2.50 15

8 2.50 16

8 2.50 17

9 2.50 18

10 2.50 19

10 2.50 20

10 2.50 21

11 2.50 22

11 2.50 23

12 2.50 24

13 2.50 25

13 2.50 26

14 2.50 27

5 2.80 8

5 2.80 9

5 2.80 10

7 2.80 11

7 2.80 12

7 2.80 13

8 2.80 14

8 2.80 15

9 2.80 16

10 2.80 17

10 2.80 18

11 2.80 19

11 2.80 20

12 2.80 21

13 2.80 22

13 2.80 23

14 2.80 24

14 2.80 25

15 2.80 26

15 2.80 27

Drainage

Trench widths Under 1.5m deep mm Over 1.5m deep mm

Pipe diameter 100mm 450 600

Pipe diameter 150mm 500 650

Pipe diameter 225mm 600 750

Pipe diameter 300mm 650 800

Volumes of filling for pipe bed and haunching (m3 per m) m3

Pipe diameter 100mm 0.117

Pipe diameter 150mm 0.152

Pipe diameter 225mm 0.195

Volumes of filling for pipe bed and surround (m3 per m)

Pipe diameter 100mm 0.185

Pipe diameter 150mm 0.231

Pipe diameter 225mm 0.285

Pipe diameter 300mm 0.391

LANDSCAPING

Tree sizes Type Height Clear stem height

Girth

Light standard 2.50-2.75m 1.50-1.80m 6-8cm

Standard 2.75-3.00m 1.8m 8-10cm

Selected standard

3.00-3.50m 1.8m 10-12cm

Heavy standard 3.50-4.00m 1.8m 12-14cm

Extra heavy standard

4.00-5.00m 1.8m 14-16cm

gm/m2 34 gm/m2 50 gm/m2 102 gm/m2 500

Bowling green (size 38.4×38.4m, area 1,475m2)

50 75 150 200

Cricket square (size 22.8×22.8m area 522m2)

18 27 54 72

Golf green (18 nr each size 570m2)

350 525 1050 1400

Lawn tennis (size 36.6×18.3m, area 670m2)

23 35 69 92

Football (size 119×91m, area 10,380m2)

368 552 1104 1472

area 6,900m2) 235 352 705 940

Hockey (size 91×55m, area 5,005m2)

170 255 510 680

Weedkiller

litres per hectare

Bowling green (size 38.4×38.4m, area 1,475m2) 1.48

Cricket square (size 22.8×22.8m, area 522m2) 0.52

Golf green (18 nr each size 570m2) 10.28

Lawn tennis (size 36.6×18.3m, area 670m2) 0.67

Football (size 119×91m, area 10,380m2) 10.83

Rugby (size 100×69m, area 6,900m2) 6.90

Hockey (size 91×55m, area 5,005m2) 5.00

CIVIL ENGINEERING OUTPUT

Placing ready-mixed concrete Labour gang (m3 per hour)

Mass concrete

blinding

150mm thick 5.50

150-300mm thick 6.25

300-500mm thick 7.00

bases

not exceeding 150mm thick 5.00

not exceeding 300mm thick 5.75

not exceeding 500mm thick 6.75

exceeding 150mm thick 7.00

sports fields Quantities of seed for

Rugby (size 100×69m,

Reinforced concrete

bases

not exceeding 300mm thick 5.50

not exceeding 500mm thick 6.25

exceeding 150mm thick 6.75

suspended slabs

not exceeding 150mm thick 3.75

not exceeding 300mm thick 4.75

exceeding 300mm thick 5.75

walls

not exceeding 150mm thick 3.50

not exceeding 300mm thick 4.50

exceeding 300mm thick 5.00

beams and columns

sectional area not exceeding 0.03m2) 2.00

sectional area not exceeding 0.03 -1.0m2) 2.50

sectional area exceeding 1.0m2) 3.50

Fixing bar reinforcement

The following figures exclude delivery, craneage and hoisting in position. The hours refer to tonnes per hour for a steelfixer and general operative

Height up to 6m (hours)

Height 7 to 12m (hours)

Height 13 to 19m (hours)

Height over 19m (hours)

Straight round bars to beams, walls, roofs and walls 0.06 0.08 0.12 0.16 to braces, columns and sloping roofs

0.06 0.08 0.12 0.16

Bent round bars to beams, walls, roofs and walls 0.04 0.06 0.06 0.08 to braces, columns and sloping

roofs 0.02 0.02 0.04 0.06

Straight, indented or square bars to beams, walls, roofs and walls 0.04 0.08 0.10 0.14 to braces, columns and sloping roofs

0.02 0.04 0.04 0.08

Bent, indented or square bars to beams, walls, roofs and walls 0.04 0.04 0.06 0.06 to braces, columns and sloping roofs

0.02 0.02 0.04 0.04

Erecting and striking formwork

Joiner m2 per hour General operative m2 per hour

Vertical wall face, height

up to 1.5m 1.70 0.80

1.5 to 3.0m 1.40 0.70

3.0 to 4.5m 1.20 0.60

4.5 to 6.0m 1.00 0.50

Horizontal slabs, height

up to 3.0m 1.11 1.11

3.0 to 3.6m 1.05 1.05

3.6 to 4.2m 1.00 1.00

4.2 to 4.8m 0.95 0.95

4.8 to 5.4m 0.90 0.90

5.4 to 6.0m 0.83 0.83

Formwork multipliers Multiplier

Battered walls 1.20

Circular walls to large radius 1.70

Circular walls to small radius 2.10

Formwork, one use 1.00

Formwork, two uses, per use 0.85

Formwork, three uses, per use 0.75

Formwork, four uses, per use 0.72

ormwork, five uses, per use 0.68

Formwork, six uses, per use 0.66

Formwork, seven uses, per use 0.63

Drainage

Unit Drainage gang (m/hour) in trenches less

than 1.5m deep

Drainage gang (m/hour) in trenches less

than 3.0m deep

Drainage gang (m/hour) in trenches less

than 4.5m deep

Lay and joint flexible-jointed clayware pipes, diameter

100mm m 10 8 7

150mm m 7 6 5

225mm m 5 4 3

300mm m 4 3 2

375mm m 3 2 2

450mm m 2 2 1

Bends

100mm nr 20 17 14

150mm nr 17 14 13

225mm nr 13 10 8

300mm nr 10 8 7

375mm nr 7 6 5

450mm nr 3 3 2

Single junctions

100mm nr 13 10 8

150mm nr 7 6 5

225mm nr 6 5 4

300mm nr 4 3 3

375mm nr 3 2 2

450mm nr 2 2 1

Precast concrete manholes Unit Pipelayer General operative

675mm diameter shaft rings m/hour 1.00 0.30

900mm diameter manhole rings m/hour 0.60 0.20

1200mm diameter manhole rings m/hour 0.40 0.10

1500mm diameter manhole rings m/hour 0.30 0.10

900 to 675mm tapers nr/hour 1.00 0.30

1200 to 675mm tapers nr/hour 0.60 0.20

900 to 675mm tapers nr/hour 0.50 0.20

Cover slabs to 675mm rings nr/hour 2.50 0.80

Cover slabs to 675mm rings nr/hour 2.00 0.70

Cover slabs to 675mm rings nr/hour 1.40 0.50

Cover slabs to 675mm rings nr/hour 0.90 0.30

Build in pipes and make good

150mm diameter nr/hour 4.00 0.00

300mm diameter nr/hour 2.00 0.00

450mm diameter nr/hour 1.00 0.00

Benching 150mm thick m2/hour 1.20 1.20

Benching 300mm thick m2/hour 0.60 0.60

Render benching 25mm thick m2/hour 1.10 1.10

Manhole cover and frame nr/hour 1.30 1.30