As you may remember, I measured success using three success measures and these same measures are used to study agile impact. These were:

Efficiency Measure Stakeholder Success Measure Success Measure

The two key sets of data gathered for the purpose of this survey were percentage or fraction of time spent planning and project success measures. For projects with agile/iterative planning components an index was created:

)(Agile Planning Effort index = total effort expended on planning

after the planning phase the total project effort in person-days

The amount of planning done in the planning phase was considered a key dataset. The planning effort index was used as the key measure of this information (more details in Appendix A). After removal of invalid data and outliers, valid agile projects totaled 1,002.