ABSTRACT

A series of recent Australian studies into construction time performance revealed that neither the building construction companies nor the client undertook any meaningful organisational learning activities from their experience of managing building and civil engineering construction projects. Post-project evaluation studies were not required for the building and civil engineering projects but this was not the case for the process engineering projects. A post-project evaluation was expected by clients and provided as part of services procured for process engineering projects.