ABSTRACT

The commitment of the rooftop owner is an important issue which will be ensured by a separate agreement between the owner and the consumer. Solar rooftop projects are complex as they also include the risk of early termination of the rooftop lease/rent agreement and the parties involved in this agreement maybe different from the parties involved under the PPA. Solar rooftop projects are complex as they also include the risk of early termination of the rooftop lease/rent agreement and the parties involved in this agreement maybe different from the parties involved under the PPA. To avoid the delays in obtaining approvals, it is important to identify all the approvals required for the particular project location and the relevant authorities who will issue the same. In case grid interconnection process has not been defined, the State Distribution Utility shall be consulted for the required procedures to be followed at the time of designing the solar rooftop power plant.