ABSTRACT

The Contractor shall, if instructed by the Engineer, search for the cause of any defect, under the direction of the Engineer. If the remedying of any defect or damage under Sub-Clause 11.1 is unduly delayed by the Contractor, a date may be fixed by the Employer, on or by which the defect or damage is to be remedied. If, during the Defects Notification Period, the Contractor considers that any defect or damage in any Plant cannot be remedied expeditiously on the Site the Contractor shall give a Notice, with reasons, to the Employer requesting consent to remove the defective or damaged Plant off the Site for the purposes of repair. Until the date 28 days after issue of the Performance Certificate, the Contractor shall have the right of access to all parts of the Works and to records of the operation, maintenance and performance of the Works, except as may be inconsistent with the Employer’s reasonable security restrictions.