ABSTRACT

The Contractor shall submit to the Engineer, not less than 42 days before the date the Contractor intends to commence the Tests on Completion, a detailed test programme showing the intended timing and resources required for these tests. If the Contractor has given a Notice under Sub-Clause 9.1 [Contractor’s Obligations] that the Works or Section are ready for Tests on Completion, and these tests are unduly delayed by the Employer’s Personnel or by a cause for which the Employer is responsible, Sub-Clause 10.3 [Interference with Tests on Completion] shall apply. The Engineer or the Contractor may require these failed tests, and the Tests on Completion on any related work, to be repeated under the same terms and conditions. The Contractor shall, except where the Employer’s Personnel have carried out the test, carry out such Works to meet the reasons set out in the Notice identifying the failure for compliance.