ABSTRACT

The Form of Tender is normally in the form of a letter with blank spaces for tenderer to insert their name and other particulars, total tender price, and other particulars of their offer. It is essential to have a standard Form of Tender and that all tenderer consistently use the same form, to make comparison of tenders easier. Secondary Option X15 states that 'the Contractor is not liable for Defects in the works due to his design so far as the author proves that author used reasonable skill and care to ensure that the author design complied with the Works Information'. The Contract Data provides the information required by the conditions of contract specific to a particular contract. Contractor's main responsibilities section is not included within the Contract Data as no entries are required. The Project Manager decides the first assessment date to suit the parties and following assessments are carried out within the assessment intervals.